1232 S MASSELIN AVE 90019
Certificate Information: 1232 S MASSELIN AVE 90019
- Application / Permit
- 24016-10000-00562
- Plan Check / Job No.
- B24LA00302
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detatched garage to 1-story ADU per GCS 65852.2(e)(1)(A). Work per WFPP. COMPLY WITH DEPARTMENT ORDER effective date 11/14/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. All permits shall be for the same time period limitation. CEIS Case Number is 995192.
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | ALEXANDER JOO |
| Corrections Issued | 1/11/2024 | ALEXANDER JOO |
| Building Plans Picked Up | 1/12/2024 | APPLICANT |
| Applicant returned to address corrections | 1/19/2024 | DANIEL SMILEY |
| Plan Check Approved | 3/26/2024 | NEHEMIAS RAMOS |
| Issued | 3/26/2024 | APPLICANT |
| CofO in Progress | 10/9/2025 | LUIS CORRAL |
| Permit Finaled | 10/9/2025 | CLAUDIO MORENO |
| CofO Issued | 10/9/2025 | CLAUDIO MORENO |
| Permit Finaled | 10/9/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/18/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2024 | CHRISTINA BRACO |
| Construction near power lines | Cleared | 3/23/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2024 | Corrections Issued | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 5/9/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Final | 5/13/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Final | 5/15/2024 | Partial Approval | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 7/24/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 8/14/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 8/16/2024 | Corrections Issued | WILLIAM MICHALAK |
| Underground Mechanical | 8/16/2024 | Partial Approval | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 8/22/2024 | Partial Approval | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 8/22/2024 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 9/3/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 9/3/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Rough | 9/3/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Drywall Nailing | 9/4/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 9/4/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Gas Test | 9/4/2024 | Partial Approval | WILLIAM MICHALAK |
| Green Building Final | 9/4/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Final | 9/4/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 9/4/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Wood Frame | 9/4/2024 | Partial Approval | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 9/12/2024 | Partial Approval | WILLIAM MICHALAK |
| Green Building Rough | 9/12/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| METHANE-Rough | 9/12/2024 | No Access for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 10/28/2024 | Corrections Issued | WILLIAM MICHALAK |
| PLUMBING-Rough | 10/28/2024 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 11/25/2024 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 11/25/2024 | Approved | WILLIAM MICHALAK |
| Final | 11/25/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Final | 11/25/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Green Building Rough | 11/25/2024 | Approved | WILLIAM MICHALAK |
| METHANE-Final | 11/25/2024 | Approved | WILLIAM MICHALAK |
| METHANE-Rough | 11/25/2024 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 11/25/2024 | Not Ready for Inspection | WILLIAM MICHALAK |
| Final | 9/9/2025 | Corrections Issued | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Not Ready | LUIS CORRAL |
| Final | 9/23/2025 | Corrections Issued | WILLIAM MICHALAK |
| Gas Test | 9/23/2025 | Corrections Issued | WILLIAM MICHALAK |
| Green Building Final | 9/23/2025 | Approved | WILLIAM MICHALAK |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Not Ready | WILLIAM MICHALAK |
| Smoke Detectors | 9/23/2025 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 10/7/2025 | Approved | LUIS CORRAL |
| Final | 10/7/2025 | Not Ready for Inspection | LUIS CORRAL |
| Gas Test | 10/7/2025 | Approved | LUIS CORRAL |
| HVAC-Final | 10/7/2025 | Approved | LUIS CORRAL |
| PLUMBING-Final | 10/7/2025 | Approved | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Not Ready | LUIS CORRAL |
| Special/Order Compliance | 10/8/2025 | Corrections Issued | LUIS CORRAL |
| Final | 10/9/2025 | OK to Issue CofO | LUIS CORRAL |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | LUIS CORRAL |