1802 W EFFIE ST 90026

Certificate Information: 1802 W EFFIE ST 90026

Application / Permit
24016-10000-00518
Plan Check / Job No.
B23LA24688
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Alteration to SFD throughout; Remove drywall, rewire electrical, upgrade plumbing, remodel kitchen, floors, windows and painting.
Permit Issued
Issued on 2/6/2024
Issuing Office
Current Status
Permit Finaled on 10/7/2024

Permit Application Status History

Submitted 1/8/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 MICHAEL LOPEZ
Corrections Issued 1/24/2024 MICHAEL LOPEZ
Quality Review Completed 1/24/2024 PRANITA SHAH
Plan Check Approved 2/5/2024 MICHAEL LOPEZ
Issued 2/6/2024 APPLICANT
Permit Finaled 10/4/2024 HAMIK HARTOUNIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Proud Crowd Inc The; Lic. No.: 1074719-B       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/9/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 5/7/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/7/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/7/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/7/2024 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/7/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Test 6/17/2024 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 6/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/18/2024 Not Ready for Inspection LILIANA PORTILLO
Deputy Wood Construction 6/20/2024 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/26/2024 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/26/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/26/2024 Partial Approval HAMIK HARTOUNIAN
Insulation 7/10/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 7/17/2024 Approved HAMIK HARTOUNIAN
Deputy Wood Construction 7/17/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 7/23/2024 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/23/2024 Partial Approval HAMIK HARTOUNIAN
Shower Pan 7/23/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 8/12/2024 Approved HAMIK HARTOUNIAN
Gas Test 8/12/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 10/4/2024 Approved HAMIK HARTOUNIAN
Final 10/4/2024 Permit Finaled HAMIK HARTOUNIAN
HVAC-Final 10/4/2024 Approved HAMIK HARTOUNIAN
PLUMBING-Final 10/4/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 10/4/2024 Approved HAMIK HARTOUNIAN
Smoke Detectors 10/4/2024 Approved HAMIK HARTOUNIAN