2349 S PARNELL AVE 90064
Certificate Information: 2349 S PARNELL AVE 90064
- Application / Permit
- 24016-10000-00485
- Plan Check / Job No.
- B23LA23044
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Alteration to (E) Det Garage and storage to convert to an ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/21/2025
- Issuing Office
- Current Status
- CofO Issued on 7/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | GEORGE JOLAKIAN |
| Corrections Issued | 1/11/2024 | GEORGE JOLAKIAN |
| Quality Review Completed | 1/23/2024 | RODOLFO ARIAS |
| Plan Check Approved | 7/23/2024 | GEORGE JOLAKIAN |
| Issued | 4/21/2025 | APPLICANT |
| CofO in Progress | 7/19/2025 | DANIEL VERA |
| Permit Finaled | 7/26/2025 | RICHARD STEINBACH |
| CofO Issued | 7/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/25/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | DARIN LAM |
| Specific Plan | Cleared | 2/7/2024 | ALESSANDRO MERCURI |
| Specific Plan | Cleared | 2/8/2024 | JULISSA LOPEZ-HODOYAN |
| Address approval | Cleared | 4/4/2024 | DIANA RENTERIA |
| Construction near power lines | Cleared | 5/17/2024 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 7/22/2024 | GEORGE JOLAKIAN |
Contact Information
| Contractor | Hoffmann Structure Inc; Lic. No.: 751137-B | 15332 ANTIOCH STREET 9 PACIFIC PALISADES, CA 90272 |
| Engineer | Youm,, Moung Han; Lic. No.: C74086 | 309 S BERENDO ST APT 6 LOS ANGELES, CA 90020 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 4/29/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 5/16/2025 | Not Ready for Inspection | DANIEL VERA |
| Deputy Wood Construction | 5/16/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2025 | Partial Approval | DANIEL VERA |
| Green Building Rough | 5/16/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 5/16/2025 | Not Ready for Inspection | DANIEL VERA |
| Underground Mechanical | 5/16/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 5/23/2025 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Partial Approval | EVAN COOPER |
| Green Building Rough | 5/23/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 5/23/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/23/2025 | Approved | EVAN COOPER |
| Underground Mechanical | 5/23/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 5/29/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Approved | DANIEL VERA |
| Green Building Rough | 5/29/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 5/29/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 6/2/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 6/2/2025 | Not Ready for Inspection | DANIEL VERA |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | DANIEL VERA |
| Shower Pan | 6/2/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | DANIEL VERA |
| Green Building Rough | 6/4/2025 | Approved | DANIEL VERA |
| HVAC-Rough | 6/4/2025 | Approved | DANIEL VERA |
| Shower Pan | 6/4/2025 | Not Ready for Inspection | DANIEL VERA |
| Wood Frame | 6/4/2025 | Approved | DANIEL VERA |
| Insulation | 6/6/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/12/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 6/12/2025 | Approved | DANIEL VERA |
| Shower Pan | 6/12/2025 | Approved | DANIEL VERA |
| Final | 7/14/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Final | 7/14/2025 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2025 | SGSOV Not Ready | DANIEL VERA |
| ELECTRICAL-Final | 7/17/2025 | Approved | DANIEL VERA |
| Final | 7/17/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 7/17/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 7/17/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | DANIEL VERA |
| Final | 7/18/2025 | OK to Issue CofO | DANIEL VERA |
| Green Building Final | 7/18/2025 | Approved | DANIEL VERA |
| METHANE-Final | 7/18/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/18/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 7/18/2025 | Approved | DANIEL VERA |