12121 W OLYMPIC BLVD 03-101 90064

Certificate Information: 12121 W OLYMPIC BLVD 03-101 90064

Application / Permit
24016-10000-00049
Plan Check / Job No.
B23LA24576
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
CHANGE OF USE FROM RETAIL TO FITNESS STUDIO: NON-STRUCURAL TENANT IMPROVEMENT (ADD NON BEARING WALLS) **ePlan**
Permit Issued
Issued on 9/4/2024
Issuing Office
Current Status
CofO Issued on 5/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 NILOOFAR MEHRAIN
Assigned to Zoning Architect 1/26/2024 NILOOFAR MEHRAIN
Corrections Issued 1/27/2024 NILOOFAR MEHRAIN
Quality Review Completed 2/1/2024 JASON HEALEY
Applicant returned to address corrections 4/11/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/30/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/8/2024 NILOOFAR MEHRAIN
Plan Check Approved 9/3/2024 NILOOFAR MEHRAIN
Issued 9/4/2024 APPLICANT
TCO Issued (Expire Date: 06-16-2026) 12/18/2025 DAVID TSAU
CofO in Progress 5/7/2026 DANIEL VARNUM
Permit Finaled 5/8/2026 VASIL MIHALEV
CofO Issued 5/8/2026 VASIL MIHALEV
Permit Finaled 5/8/2026 VASIL MIHALEV

Permit Application Clearance Information

Green Code Cleared 4/4/2024 AARON COSTA
CPC Cleared 5/7/2024 GEORGIA SMITH
Eng Process Fee Ord 176,300 Cleared 5/7/2024 DARIN LAM
Sewer availability Cleared 5/7/2024 DARIN LAM
Tract Map conditions Cleared 5/7/2024 GEORGIA SMITH
ZA Case Cleared 5/7/2024 GEORGIA SMITH
ZA Case Cleared 5/7/2024 GEORGIA SMITH
Miscellaneous Cleared 5/24/2024 DINAH GARIN
Specific Plan Cleared 6/7/2024 PEDRO AYALA
Specific Plan Cleared 6/7/2024 PEDRO AYALA
DAS Clearance Cleared 6/10/2024 Lawrence Quirante
Specific Plan Cleared 7/10/2024 JULISSA LOPEZ-HODOYAN
ZI Cleared 7/10/2024 JULISSA LOPEZ-HODOYAN
Fire Marshal Fire Life Safety Cleared 7/22/2024 WILLIAM JOHNS
Zoning Plan Check Cleared 9/3/2024 Lawrence Quirante

Contact Information

Architect Levine,, Mark Edward; Lic. No.: NA30669       ,
Contractor Calbuild Construction Inc; Lic. No.: 1107250-B       ,

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 11/21/2024 Conditional Approval CASIMIR BRITTON
Drywall Nailing 6/6/2025 Partial Approval CASIMIR BRITTON
Insulation 6/20/2025 No Access for Inspection DANIEL VARNUM
Drywall Nailing 7/11/2025 Partial Approval CASIMIR BRITTON
Light Gage Steel Frame 7/17/2025 Partial Approval CASIMIR BRITTON
Drywall Nailing 8/18/2025 Partial Approval CASIMIR BRITTON
Light Gage Steel Frame 8/18/2025 Partial Approval CASIMIR BRITTON
Special/Order Compliance 8/18/2025 Corrections Issued CASIMIR BRITTON
Drywall Nailing 8/20/2025 Approved CASIMIR BRITTON
Drywall Nailing 8/21/2025 Partial Approval DANIEL VARNUM
Drywall Nailing 8/22/2025 Partial Approval DERRICK SPENCER
Drywall Nailing 8/26/2025 Approved DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/26/2025 Approved DANIEL VARNUM
Pre-Inspection 9/15/2025 Partial Inspection CASIMIR BRITTON
Partition/T-Bar Ceiling 10/2/2025 Corrections Issued CASIMIR BRITTON
Partition/T-Bar Ceiling 10/3/2025 Not Ready for Inspection CASIMIR BRITTON
Partition/T-Bar Ceiling 10/10/2025 Not Ready for Inspection CASIMIR BRITTON
Partition/T-Bar Ceiling 10/17/2025 Not Ready for Inspection CASIMIR BRITTON
T-Bar Ceiling 10/30/2025 Not Ready for Inspection CASIMIR BRITTON
Final 12/4/2025 Not Ready for Inspection CASIMIR BRITTON
Final 12/4/2025 Not Ready for Inspection DANIEL VARNUM
Green Building Final 12/4/2025 Approved CASIMIR BRITTON
Green Building Rough 12/4/2025 Approved CASIMIR BRITTON
Reinforced Masonry Frame 12/4/2025 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 12/4/2025 Approved CASIMIR BRITTON
Special/Order Compliance 12/4/2025 Partial Approval SCOTT SOBEL
Special/Order Compliance 1/2/2026 Partial Inspection CASIMIR BRITTON
Final 5/7/2026 OK to Issue CofO DANIEL VARNUM
Reinforced Concrete Frame 5/7/2026 Approved DANIEL VARNUM