743 1/2 E 78TH ST 90001

Certificate Information: 743 1/2 E 78TH ST 90001

Application / Permit
24014-70000-05617
Plan Check / Job No.
B24SL01018
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of existing garage into ADU per ordinance.
Permit Issued
Issued on 4/1/2025
Issuing Office
South Los Angeles
Current Status
Issued on 4/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2024 APPLICANT
Assigned to Plan Check Engineer 12/26/2024 RICARDO RAMIREZ
Corrections Issued 12/26/2024 RICARDO RAMIREZ
Building Plans Picked Up 12/31/2024 APPLICANT
Applicant returned to address corrections 3/27/2025 RICARDO RAMIREZ
Issued 4/1/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/4/2025 JEANIE LAM
Roof/Waste drainage to street Cleared 2/4/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/12/2025 JEANIE LAM
Sewer availability Cleared 2/12/2025 JEANIE LAM
Construction near power lines Cleared 2/18/2025 RIDWAN HARDY

Contact Information

Contractor Redoak Construction Inc; Lic. No.: 1035723-B 7313 WALNUT DRIVE      LOS ANGELES, CA 90001
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/11/2025 Partial Approval JOHN QUINTANILLA
Footing/Foundation/Slab 4/16/2025 Approved JOHN QUINTANILLA
Drywall Nailing 4/24/2025 Partial Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Approved JOHN QUINTANILLA
Gas Test 4/24/2025 Approved JOHN QUINTANILLA
Underground Mechanical 4/24/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 5/5/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 5/5/2025 Corrections Issued JOHN QUINTANILLA
Green Building Rough 5/5/2025 Not Ready for Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 5/5/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 5/5/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 5/7/2025 Approved JOHN QUINTANILLA
HVAC-Rough 5/7/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 5/7/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 5/12/2025 Approved SABAS ALONSO
Green Building Rough 5/12/2025 Approved SABAS ALONSO
Insulation 5/12/2025 Corrections Issued SABAS ALONSO
Insulation 5/14/2025 Conditional Approval JOHN QUINTANILLA
Insulation 5/16/2025 Approved JOHN QUINTANILLA
Drywall Nailing 5/21/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 7/30/2025 SGSOV Not Ready BARRY HACHE
ELECTRICAL-Final 8/1/2025 Corrections Issued LUIS CASTRO
HVAC-Final 8/1/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 8/1/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Final 9/2/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 9/2/2025 Conditional Approval JOHN QUINTANILLA
PLUMBING-Final 9/2/2025 Approved JOHN QUINTANILLA
Final 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 10/14/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 10/16/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 10/16/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 10/16/2025 Approved JOHN QUINTANILLA
HVAC-Final 10/16/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/16/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 10/16/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 10/22/2025 Approved JOHN QUINTANILLA
Final 10/22/2025 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/22/2025 SGSOV Approved JOHN QUINTANILLA