2125 1/2 S CARMONA AVE 90016

Certificate Information: 2125 1/2 S CARMONA AVE 90016

Application / Permit
24014-70000-04551
Plan Check / Job No.
B24SL00756
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage and an existing (14'5"x18'5") unpermitted structure built prior to 2020 to an Accessory Dwelling Unit per GCS 65852.2(d)(2)
Permit Issued
Issued on 7/15/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 10/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2024 APPLICANT
Assigned to Plan Check Engineer 10/15/2024 RICARDO RAMIREZ
Corrections Issued 10/16/2024 RICARDO RAMIREZ
Building Plans Picked Up 11/17/2024 APPLICANT
Plan Check Approved 7/10/2025 RICARDO RAMIREZ
Issued 7/15/2025 APPLICANT
CofO in Progress 10/1/2025 ARTHUR NEGRETE
Permit Finaled 10/8/2025 DEROLD HAUFF
CofO Issued 10/8/2025 DEROLD HAUFF
Permit Finaled 10/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/2/2025 RIDWAN HARDY
Address approval Cleared 5/8/2025 JEANIE LAM
Tenant Habitability Plan Cleared 6/10/2025 KORNEL LELEA
Roof/Waste drainage to street Cleared 6/25/2025 JEREMY CHOK
Sewer availability Cleared 6/26/2025 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 7/7/2025 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/23/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 8/21/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Approved ARTHUR NEGRETE
Green Building Rough 8/21/2025 Approved ARTHUR NEGRETE
Insulation 8/21/2025 Corrections Issued ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 8/21/2025 Approved ARTHUR NEGRETE
Drywall Nailing 8/25/2025 Approved ARTHUR NEGRETE
Final 9/12/2025 Not Ready for Inspection WILLIAM SIERRA
Footing/Foundation/Slab 9/12/2025 Not Ready for Inspection WILLIAM SIERRA
Green Building Final 9/12/2025 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready WILLIAM SIERRA
Smoke Detectors 9/12/2025 Not Ready for Inspection WILLIAM SIERRA
Final 9/18/2025 Corrections Issued ARTHUR NEGRETE
Footing/Foundation/Slab 9/18/2025 Corrections Issued ARTHUR NEGRETE
Green Building Final 9/18/2025 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 9/18/2025 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 9/19/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 9/23/2025 Approved ARTHUR NEGRETE
Final 9/23/2025 Corrections Issued ARTHUR NEGRETE
Green Building Final 9/23/2025 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 9/23/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 9/23/2025 Approved ARTHUR NEGRETE
Smoke Detectors 9/23/2025 Approved ARTHUR NEGRETE
Final 9/30/2025 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 9/30/2025 Approved ARTHUR NEGRETE