231 W 91ST ST 90003
Certificate Information: 231 W 91ST ST 90003
- Application / Permit
- 24014-70000-04510
- Plan Check / Job No.
- B24SL00745
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bathroom addition to rear of dwelling.
- Permit Issued
- Issued on 12/10/2024
- Issuing Office
- Current Status
- Issued on 12/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2024 | RICARDO RAMIREZ |
| Corrections Issued | 10/15/2024 | RICARDO RAMIREZ |
| Building Plans Picked Up | 10/22/2024 | APPLICANT |
| Applicant returned to address corrections | 10/31/2024 | RICARDO RAMIREZ |
| Plan Check Approved | 11/5/2024 | RICARDO RAMIREZ |
| Issued | 12/10/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2024 | BIJAN ZADEH |
| Roof/Waste drainage to street | Cleared | 11/4/2024 | BIJAN ZADEH |
Contact Information
| Contractor | R R Building And Painting Contractors; Lic. No.: 585113-B | 6332 VERMONT LONG BEACH, CA 90803 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/17/2024 | Partial Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 1/22/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/22/2025 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 2/18/2025 | Conditional Approval | JOHN QUINTANILLA |
| Wood Frame | 2/25/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 4/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 4/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/23/2025 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/27/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 5/27/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/27/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/23/2026 | Approved | LUIS CASTRO |
| Final | 3/23/2026 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 3/23/2026 | Not Ready for Inspection | LUIS CASTRO |
| Green Building Rough | 3/23/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 3/23/2026 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 3/23/2026 | Approved | LUIS CASTRO |
| Final | 4/28/2026 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Final | 4/28/2026 | Approved | JOHN QUINTANILLA |