161 W 82ND ST 90003
Certificate Information: 161 W 82ND ST 90003
- Application / Permit
- 24014-70000-03984
- Plan Check / Job No.
- B24SL00636
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bedroom and bathroom addition to rear of dwelling. Framing to comply with wood framing perscriptive provisions. Remodel existing bathroom and bedrooms.
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | RICARDO RAMIREZ |
| Corrections Issued | 9/5/2024 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 9/6/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 9/17/2024 | RICARDO RAMIREZ |
| Issued | 9/24/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | JOHN QUINTANILLA |
| Permit Finaled | 5/8/2025 | DEROLD HAUFF |
| CofO Issued | 5/8/2025 | DEROLD HAUFF |
| Permit Finaled | 5/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/5/2024 | CELINA MORENO |
| Sewer availability | Cleared | 9/5/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2024 | TREVOR QUAN |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | PO BOX 39459 DOWNEY, CA 90241 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 10/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 10/8/2024 | Corrections Issued | CRAIG DAVIS |
| Order to Comply | 10/8/2024 | Not Required | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 10/18/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 12/10/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 12/10/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 12/10/2024 | Corrections Issued | CRAIG DAVIS |
| Sewer | 12/10/2024 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 12/17/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Order to Comply | 12/17/2024 | Not Required | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/17/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Sewer | 12/17/2024 | Partial Approval | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/20/2024 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 12/20/2024 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 12/24/2024 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/24/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/6/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 1/6/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 1/6/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/17/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 1/17/2025 | Conditional Approval | JOHN QUINTANILLA |
| Insulation | 1/22/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 1/27/2025 | Approved | JOHN QUINTANILLA |
| Shower Pan | 2/4/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 2/6/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Final | 3/7/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 3/7/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Final | 3/11/2025 | Conditional Approval | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Final | 5/2/2025 | OK to Issue CofO | JOHN QUINTANILLA |