347-349 E 75TH ST 90003

Certificate Information: 347-349 E 75TH ST 90003

Application / Permit
24014-70000-03425
Plan Check / Job No.
B24SL00525
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
One story addition to rear of duplex. Addition of new bedrooms and bathrooms. Remodel of existing bedrooms, bathrooms and kitchens. Add laundry area inside each unit. Framing to comply with wood frame perscriptive provisions.
Permit Issued
Issued on 9/10/2024
Issuing Office
South Los Angeles
Current Status
CofO Issued on 7/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/6/2024 RICARDO RAMIREZ
Corrections Issued 8/7/2024 RICARDO RAMIREZ
Building Plans Picked Up 8/13/2024 APPLICANT
Applicant returned to address corrections 9/3/2024 RICARDO RAMIREZ
Issued 9/10/2024 APPLICANT
CofO in Progress 7/2/2025 JOHN QUINTANILLA
Permit Finaled 7/6/2025 DEROLD HAUFF
CofO Issued 7/6/2025 DEROLD HAUFF
Permit Finaled 7/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/20/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/23/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 8/26/2024 TREVOR QUAN
Community Plan Implem. Overlay Cleared 8/28/2024 ANACANY HURTADO
ZI Cleared 8/28/2024 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2024 Conditional Approval ALEX COLIN
Footing/Foundation/Slab 10/3/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 12/4/2024 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 12/6/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 1/10/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Rough 1/10/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 1/10/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 1/15/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 1/15/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 1/15/2025 Approved JOHN QUINTANILLA
Insulation 1/21/2025 Conditional Approval JOHN QUINTANILLA
Drywall Nailing 1/30/2025 Approved ANTHONY RAMOS
Insulation 1/30/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 1/30/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 4/7/2025 Corrections Issued JOHN QUINTANILLA
Final 4/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 4/7/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 4/7/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Final 4/7/2025 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 4/7/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 4/10/2025 Approved JOHN QUINTANILLA
Green Building Final 4/10/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 4/11/2025 Approved JOHN QUINTANILLA
Final 4/15/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 4/15/2025 Conditional Approval JOHN QUINTANILLA
PLUMBING-Rough 4/15/2025 Approved JOHN QUINTANILLA
HVAC-Final 5/13/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 5/13/2025 Approved JOHN QUINTANILLA
Final 5/21/2025 Conditional Approval JOHN QUINTANILLA
Final 7/1/2025 OK to Issue CofO JOHN QUINTANILLA