347-349 E 75TH ST 90003
Certificate Information: 347-349 E 75TH ST 90003
- Application / Permit
- 24014-70000-03425
- Plan Check / Job No.
- B24SL00525
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- One story addition to rear of duplex. Addition of new bedrooms and bathrooms. Remodel of existing bedrooms, bathrooms and kitchens. Add laundry area inside each unit. Framing to comply with wood frame perscriptive provisions.
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 7/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2024 | RICARDO RAMIREZ |
| Corrections Issued | 8/7/2024 | RICARDO RAMIREZ |
| Building Plans Picked Up | 8/13/2024 | APPLICANT |
| Applicant returned to address corrections | 9/3/2024 | RICARDO RAMIREZ |
| Issued | 9/10/2024 | APPLICANT |
| CofO in Progress | 7/2/2025 | JOHN QUINTANILLA |
| Permit Finaled | 7/6/2025 | DEROLD HAUFF |
| CofO Issued | 7/6/2025 | DEROLD HAUFF |
| Permit Finaled | 7/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/20/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 8/23/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | TREVOR QUAN |
| Community Plan Implem. Overlay | Cleared | 8/28/2024 | ANACANY HURTADO |
| ZI | Cleared | 8/28/2024 | ANACANY HURTADO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/2/2024 | Conditional Approval | ALEX COLIN |
| Footing/Foundation/Slab | 10/3/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 12/4/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/15/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/15/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 1/15/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 1/21/2025 | Conditional Approval | JOHN QUINTANILLA |
| Drywall Nailing | 1/30/2025 | Approved | ANTHONY RAMOS |
| Insulation | 1/30/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 1/30/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 4/7/2025 | Corrections Issued | JOHN QUINTANILLA |
| Final | 4/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Final | 4/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 4/7/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 4/7/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 4/10/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 4/10/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Service/Power Release | 4/11/2025 | Approved | JOHN QUINTANILLA |
| Final | 4/15/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 4/15/2025 | Conditional Approval | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/15/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 5/13/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 5/13/2025 | Approved | JOHN QUINTANILLA |
| Final | 5/21/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 7/1/2025 | OK to Issue CofO | JOHN QUINTANILLA |