2627 S VETERAN AVE 90064

Certificate Information: 2627 S VETERAN AVE 90064

Application / Permit
24014-70000-02521
Plan Check / Job No.
B24SL00114
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition to side and rear of dwelling. Remodel existing bathrooms and bedrooms. Framing per engineers design.
Permit Issued
Issued on 6/27/2024
Issuing Office
South Los Angeles
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 6/11/2024 RICARDO RAMIREZ
Corrections Issued 6/11/2024 RICARDO RAMIREZ
Building Plans Picked Up 6/18/2024 APPLICANT
Issued 6/27/2024 APPLICANT
Permit Finaled 4/22/2025 RICHARD STEINBACH
CofO Issued 4/22/2025 RICHARD STEINBACH
Permit Finaled 4/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/20/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 6/20/2024 DIANA RENTERIA
Sewer availability Cleared 6/20/2024 KIMBERLY HERNANDEZ
Grading Pre-Inspection Cleared 6/27/2024 SERGIO VALENZUELA

Contact Information

Architect Choi,, S King; Lic. No.: C38125 800 E OCEAN BLVD #703      LONG BEACH, CA 90802
Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/22/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/3/2024 Corrections Issued DANIEL VERA
Footing/Foundation/Slab 9/6/2024 Approved KENNETH NAGLE
PLUMBING-Rough 9/30/2024 Approved KIRK SANDERS
Wood Frame 9/30/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 10/4/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Approved DANIEL VERA
Deputy Wood Construction 11/21/2024 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Approved DANIEL VERA
ELECTRICAL-Rough 12/26/2024 Approved SEAN HAUPT
Green Building Rough 12/26/2024 Corrections Issued SEAN HAUPT
HVAC-Rough 12/26/2024 Approved SEAN HAUPT
PLUMBING-Rough 12/26/2024 Approved SEAN HAUPT
Underground Mechanical 1/7/2025 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 1/13/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Approved DANIEL VERA
Green Building Rough 1/13/2025 Approved DANIEL VERA
Interior/Exterior Lathing 1/13/2025 Partial Approval DANIEL VERA
Insulation 1/15/2025 Approved DANIEL VERA
Drywall Nailing 1/31/2025 Approved EVAN COOPER
Interior/Exterior Lathing 1/31/2025 Approved EVAN COOPER
Shower Pan 1/31/2025 Approved EVAN COOPER
Service/Power Release 2/12/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 3/7/2025 Partial Approval BOBBY KEY
Service/Power Release 3/7/2025 Approved BOBBY KEY
Special/Order Compliance 3/7/2025 Partial Inspection WILBER ROSALES
Final 3/27/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/27/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 3/27/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 4/11/2025 Approved TEMISTOCLES CAAL
Final 4/11/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 4/11/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 4/11/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/11/2025 SGSOV Approved TEMISTOCLES CAAL
Final 4/22/2025 Conditional Approval MICHAEL PELHAM