245 1/2 E 64TH ST 90003

Certificate Information: 245 1/2 E 64TH ST 90003

Application / Permit
24014-70000-01087
Plan Check / Job No.
B24SL00042
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to ADU per state law. Small storage addition to side of ADU.
Permit Issued
Issued on 8/13/2024
Issuing Office
South Los Angeles
Current Status
CofO Issued on 5/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2024 APPLICANT
Assigned to Plan Check Engineer 3/19/2024 RICARDO RAMIREZ
Corrections Issued 3/21/2024 RICARDO RAMIREZ
Issued 8/13/2024 APPLICANT
CofO in Progress 5/16/2025 MICHAEL LEWIS
Permit Finaled 5/22/2025 DEROLD HAUFF
CofO Issued 5/22/2025 DEROLD HAUFF
Permit Finaled 5/22/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/6/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 4/6/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/15/2024 CELINA MORENO
Sewer availability Cleared 4/15/2024 CELINA MORENO
Community Plan Implem. Overlay Cleared 5/14/2024 XIAOLIN LI
ZI Cleared 5/14/2024 XIAOLIN LI
Construction near power lines Cleared 8/5/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/29/2024 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 9/4/2024 Approved MICHAEL LEWIS
Sewer 9/25/2024 Approved MICHAEL LEWIS
Underground Mechanical 9/25/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 10/16/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 10/16/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 10/28/2024 Partial Approval MICHAEL LEWIS
Green Building Rough 10/28/2024 Approved MICHAEL LEWIS
HVAC-Rough 10/28/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/28/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 10/28/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved JOSH MEISTER
Insulation 11/12/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 12/16/2024 Approved JOHN QUINTANILLA
Underground Mechanical 12/16/2024 Approved JOHN QUINTANILLA
Drywall Nailing 12/19/2024 Approved JOHN QUINTANILLA
ELECTRICAL-Final 2/20/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 3/11/2025 Approved MICHAEL LEWIS
Final 3/11/2025 Corrections Issued MICHAEL LEWIS
Green Building Final 3/11/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 3/11/2025 Approved MICHAEL LEWIS
Final 4/15/2025 Corrections Issued MICHAEL LEWIS
Final 5/14/2025 OK to Issue CofO JOHN QUINTANILLA