815 W 101ST ST 90044
Certificate Information: 815 W 101ST ST 90044
- Application / Permit
- 24014-70000-00513
- Plan Check / Job No.
- B24SL00020
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of a (20'0" x 18'0") garage and existing (14'0" x 18'0") unpermitted structure built prior to Jan 1 2018 to an Accessory Dwelling Unit PER GCS65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2024 | RICARDO RAMIREZ |
| Corrections Issued | 2/8/2024 | RICARDO RAMIREZ |
| Building Plans Picked Up | 2/8/2024 | APPLICANT |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 10/7/2024 | BEN MOLSTAD |
| Permit Finaled | 10/8/2024 | DEROLD HAUFF |
| CofO Issued | 10/8/2024 | DEROLD HAUFF |
| Permit Finaled | 10/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/15/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/15/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2024 | JEANIE LAM |
| Sewer availability | Cleared | 2/16/2024 | JEANIE LAM |
| Construction near power lines | Cleared | 6/21/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/18/2024 | Conditional Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/22/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 7/22/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Sewer | 7/22/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Underground Mechanical | 7/22/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 8/6/2024 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 8/7/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/7/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/8/2024 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 8/8/2024 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 8/8/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/9/2024 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 8/9/2024 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 8/9/2024 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 8/9/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/12/2024 | No Access for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/12/2024 | No Access for Inspection | JOSEPH MCGARRY |
| Underground Mechanical | 8/12/2024 | No Access for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 8/14/2024 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 8/14/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 8/21/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 8/28/2024 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/28/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/25/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 9/25/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 9/25/2024 | Approved | BEN MOLSTAD |
| Gas Test | 9/25/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 9/25/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 9/25/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 9/25/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 9/25/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 9/25/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 10/7/2024 | Approved | BEN MOLSTAD |
| Final | 10/7/2024 | OK to Issue CofO | BEN MOLSTAD |
| HVAC-Final | 10/7/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 10/7/2024 | Approved | BEN MOLSTAD |