9603-9605 N CEDROS AVE 91402

Certificate Information: 9603-9605 N CEDROS AVE 91402

Application / Permit
24014-70000-00405
Plan Check / Job No.
B24SL00015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Small addition (274sf) & convert portion of (e) dwelling (513sf) to create ADU (787sf) PER LAMC 12.22 A.33(c) AND (e).
Permit Issued
Issued on 2/21/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2024 APPLICANT
Assigned to Plan Check Engineer 2/1/2024 RICARDO RAMIREZ
Corrections Issued 2/1/2024 RICARDO RAMIREZ
Building Plans Picked Up 2/8/2024 APPLICANT
Plan Check Approved 2/15/2024 RICARDO RAMIREZ
Issued 2/21/2024 APPLICANT
CofO in Progress 3/5/2025 JENNIFER RABUCHIN
Permit Finaled 3/15/2025 RUBEN SALAS
CofO Issued 3/15/2025 RUBEN SALAS
Permit Finaled 3/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/13/2024 CARLOS AGUILERA
Miscellaneous Cleared 2/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/14/2024 CARLOS AGUILERA
Sewer availability Cleared 2/14/2024 CARLOS AGUILERA

Contact Information

Architect Garcia,, Hugo; Lic. No.: C33055 6429 DOS RIOS ROAD      DOWNEY, CA 90240
Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/31/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 5/31/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/24/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/10/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/10/2024 Approved JENNIFER RABUCHIN
Green Building Rough 7/10/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/10/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 7/10/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/22/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 7/22/2024 Approved JENNIFER RABUCHIN
Insulation 7/22/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 7/22/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 7/29/2024 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 8/21/2024 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 8/21/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 8/27/2024 Partial Approval JENNIFER RABUCHIN
Shower Pan 9/19/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/26/2024 Approved JENNIFER RABUCHIN
Final 2/6/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/6/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/6/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/28/2025 Approved JENNIFER RABUCHIN
Final 2/28/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 2/28/2025 Approved JENNIFER RABUCHIN
HVAC-Final 2/28/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/28/2025 Approved JENNIFER RABUCHIN
Service/Power Release 2/28/2025 Approved JENNIFER RABUCHIN