8441 1/2 S KITTYHAWK AVE 90045
Certificate Information: 8441 1/2 S KITTYHAWK AVE 90045
- Application / Permit
- 24014-40000-03533
- Plan Check / Job No.
- B24SP02881
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 18' X 20' GARAGE CONVERSION INTO A.D.U. WITH EXPANSION IN FLOOR AREA. CONST. PER W.F.P.P.
- Permit Issued
- Issued on 6/5/2025
- Issuing Office
- San Pedro
- Current Status
- Issued on 6/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/13/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/5/2024 | APPLICANT |
| Plan Check Approved | 10/24/2024 | TSE MING HUANG |
| Issued | 6/5/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 9/21/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 9/21/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 10/19/2024 | HAMID GHAEMMAGHAMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Assink,, Aart; Lic. No.: C39390 | 1611 EL PRADO AVE TORRANCE, CA 90501 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/9/2025 | Partial Approval | JESUS PINEDA |
| Sewer | 6/9/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 6/9/2025 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 6/12/2025 | Approved | JESUS PINEDA |
| Special/Order Compliance | 6/12/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Approved | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 7/10/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 8/7/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/8/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 8/8/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 10/31/2025 | Approved | JESUS PINEDA |
| Final | 10/31/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 10/31/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 10/31/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/31/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | JESUS PINEDA |