1224 W 251ST ST 90710
Certificate Information: 1224 W 251ST ST 90710
- Application / Permit
- 24014-40000-01180
- Plan Check / Job No.
- B24SP00060
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED KITCHEN AND BEDROOM ADDITION. INCLUDES REMODEL OF (E) PORTION OF SFD.
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Metro
- Current Status
- Issued on 5/29/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/27/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/4/2024 | APPLICANT |
| Applicant returned to address corrections | 5/2/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 5/14/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 5/28/2024 | YAQUB MIRZA |
| Issued | 5/29/2024 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/2/2024 | SPENCER WEJROWSKI |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2024 | JILVER MAZARIEGOS |
| Roof/Waste drainage to street | Cleared | 5/7/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Nkc Builder; Lic. No.: 1075858-B | 1107 13TH AVE DELANO, CA 93215 |
| Engineer | Lara,, David Antonio; Lic. No.: C87203 | 4700 LINCOLN RD NE ALBUQUERQUE, NM 87109 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2024 | Corrections Issued | EUGENE CASSIDY |
| METHANE-Barrier | 6/11/2024 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 6/11/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/11/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/18/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/3/2024 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/28/2024 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/28/2024 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 8/28/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/28/2024 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 8/28/2024 | Partial Approval | EUGENE CASSIDY |
| Insulation | 9/5/2024 | Corrections Issued | JOSEPH MCGARRY |
| Drywall Nailing | 9/11/2024 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/11/2024 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/27/2025 | Approved | EUGENE CASSIDY |
| Insulation | 5/27/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/27/2025 | Approved | EUGENE CASSIDY |