1631-1631 1/2 W 54TH ST 90062

Certificate Information: 1631-1631 1/2 W 54TH ST 90062

Application / Permit
24014-30002-01054
Plan Check / Job No.
B24WL01211
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental ref to pcis # 24014-10000-01054, to add an attached ADU (2-story) at rear per LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/24/2024
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 RICHARD GARCIA
Corrections Issued 6/7/2024 RICHARD GARCIA
Building Plans Picked Up 6/11/2024 APPLICANT
Applicant returned to address corrections 6/13/2024 EDWIN ESPIN
Plan Check Approved 6/24/2024 CAROLEAN BASMA
Issued 6/24/2024 APPLICANT
Permit Finaled 10/30/2024 JOSE MACIAS

Permit Application Clearance Information

Address approval Cleared 6/12/2024 CELINA MORENO
Roof/Waste drainage to street Cleared 6/12/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/13/2024 JEANIE LAM
Sewer availability Cleared 6/13/2024 JEANIE LAM
Community Plan Implem. Overlay Cleared 6/20/2024 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 PO BOX 40237      DOWNEY, CA 90239

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/5/2024 Corrections Issued CRAIG DAVIS
Underground Mechanical 7/9/2024 Corrections Issued CRAIG DAVIS
Pre-Inspection 7/15/2024 Not Ready for Inspection DAVID FEILER
Underground Mechanical 7/15/2024 Corrections Issued DAVID FEILER
Pre-Inspection 7/22/2024 Partial Inspection ANTHONY EGSON
Underground Mechanical 7/22/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 7/26/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 8/30/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 8/30/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/30/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 9/3/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 9/3/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 9/3/2024 Corrections Issued CRAIG DAVIS
Wood Frame 9/3/2024 Partial Approval CRAIG DAVIS
Shower Pan 9/4/2024 Approved CRAIG DAVIS
Insulation 9/6/2024 Not Ready for Inspection ALEX COLIN
Insulation 9/9/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 9/9/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 9/10/2024 Approved JOSE MACIAS
PLUMBING-Rough 9/10/2024 Approved JOSE MACIAS
Drywall Nailing 9/13/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 9/19/2024 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 9/20/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 10/23/2024 Approved JOSE MACIAS
Green Building Final 10/23/2024 Approved JOSE MACIAS
Green Building Rough 10/23/2024 Approved JOSE MACIAS
Smoke Detectors 10/23/2024 Approved JOSE MACIAS
Final 10/24/2024 Not Ready for Inspection JOSE MACIAS
Deputy Wood Construction 10/25/2024 Conditional Approval JOSE MACIAS
Final 10/30/2024 Permit Finaled JOSE MACIAS