7825 S KENTWOOD AVE 90045

Certificate Information: 7825 S KENTWOOD AVE 90045

Application / Permit
24014-30000-05723
Plan Check / Job No.
B24WL10086
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND A 2ND STORY ADDITION ON AN (E) SFD
Permit Issued
Issued on 6/2/2025
Issuing Office
West Los Angeles
Current Status
Issued on 6/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/30/2024 APPLICANT
Assigned to Plan Check Engineer 1/8/2025 KAVIAN REFAHI
Plans on Hold 1/13/2025 KAVIAN REFAHI
Hold Released 1/27/2025 KAVIAN REFAHI
Corrections Issued 1/27/2025 KAVIAN REFAHI
Quality Review Completed 2/3/2025 CHIHARU SUZUKI
Building Plans Picked Up 2/4/2025 APPLICANT
Applicant returned to address corrections 4/25/2025 KAVIAN REFAHI
Applicant returned to address corrections 5/7/2025 KAVIAN REFAHI
Plan Check Approved 5/19/2025 KAVIAN REFAHI
Issued 6/2/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/20/2025 KIMBERLY HERNANDEZ
Sewer availability Cleared 2/20/2025 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 2/22/2025 LIAM ODONOVAN
Construction near power lines Cleared 4/9/2025 RIDWAN HARDY
GPI Written Notices Cleared 5/19/2025 KAVIAN REFAHI
Grading Pre-Inspection Cleared 5/19/2025 KAVIAN REFAHI

Contact Information

Contractor Owner-Builder       ,
Engineer Shirley,, Peter; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/8/2025 Approved RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 8/22/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 8/22/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Inspection RUBEN RIVAS
Green Building Rough 9/11/2025 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/20/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 10/22/2025 Corrections Issued RUBEN RIVAS
Green Building Rough 10/22/2025 Not Ready for Inspection RUBEN RIVAS
Wood Frame 11/7/2025 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Approved RUBEN RIVAS
Green Building Rough 11/12/2025 Not Ready for Inspection RUBEN RIVAS
HVAC-Rough 12/5/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 1/9/2026 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 1/9/2026 Approved ANTHONY EGSON
HVAC-Rough 1/12/2026 Approved ANTHONY EGSON
Pre-Inspection 1/15/2026 Partial Inspection ANTHONY EGSON
Pre-Inspection 1/23/2026 Partial Inspection ANTHONY EGSON
Insulation 2/2/2026 Approved ANTHONY EGSON
Drywall Nailing 2/10/2026 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/18/2026 Approved ANTHONY EGSON
Shower Pan 3/18/2026 Approved ANTHONY EGSON