321 S KENTER AVE 90049

Certificate Information: 321 S KENTER AVE 90049

Application / Permit
24014-30000-05694
Plan Check / Job No.
B24WL10061
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2nd story addition to (E) 1-stort SFD by keeping portion of existing foundation and wall with new attached 2-car garage and attached ADU per Ordinance (LAMC 12.22 A.33(c)&(e)).
Permit Issued
Issued on 3/6/2025
Issuing Office
West Los Angeles
Current Status
Issued on 3/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/26/2024 APPLICANT
Assigned to Plan Check Engineer 12/31/2024 HOOMAN HAJIZADEH
Corrections Issued 1/7/2025 HOOMAN HAJIZADEH
Quality Review Completed 1/16/2025 CHIHARU SUZUKI
Building Plans Picked Up 1/17/2025 APPLICANT
Plan Check Approved 3/4/2025 HOOMAN HAJIZADEH
Issued 3/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/11/2025 DARIN LAM
Low Impact Development (LID) Cleared 1/14/2025 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 1/17/2025 DARIN LAM
Roof/Waste drainage to street Cleared 1/17/2025 DARIN LAM
Sewer availability Cleared 1/17/2025 DARIN LAM
Specific Plan Cleared 1/28/2025 JOSHUA JONES
GPI Written Notices Cleared 3/4/2025 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 3/4/2025 HOOMAN HAJIZADEH

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/21/2025 Corrections Issued HERBERT GIRON
Special/Order Compliance 5/21/2025 Corrections Issued HERBERT GIRON
Pre-Inspection 8/25/2025 Partial Inspection HERBERT GIRON
PLUMBING-Rough 9/8/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 10/20/2025 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval HERBERT GIRON
Deputy Wood Construction 1/13/2026 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/15/2026 Approved HERBERT GIRON
PLUMBING-Rough 2/26/2026 Corrections Issued HERBERT GIRON
HVAC-Rough 3/11/2026 Corrections Issued HERBERT GIRON
PLUMBING-Rough 3/11/2026 Approved HERBERT GIRON
HVAC-Rough 4/2/2026 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 4/10/2026 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 4/22/2026 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/28/2026 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 5/5/2026 Partial Approval HERBERT GIRON
HVAC-Rough 5/5/2026 Approved HERBERT GIRON
Interior/Exterior Lathing 5/5/2026 Partial Approval HERBERT GIRON
Verify Sprinkler Sign Off 5/5/2026 Approved HERBERT GIRON
Insulation 5/14/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 5/21/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 5/21/2026 Not Ready for Inspection ANTHONY EGSON
Insulation 5/21/2026 Approved ANTHONY EGSON
Shower Pan 6/1/2026 Approved HERBERT GIRON