3759 S WADE ST 90066
Certificate Information: 3759 S WADE ST 90066
- Application / Permit
- 24014-30000-05243
- Plan Check / Job No.
- B24WL09318
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of an (E) garage with an addition to create a new 1-story ADU per LAMC 12.22 A .33 (c) and (e). Design per licensed engineer.
- Permit Issued
- Issued on 11/4/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2024 | RICHARD GARCIA |
| Corrections Issued | 11/29/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 12/10/2024 | APPLICANT |
| Plan Check Approved | 9/4/2025 | CAROLEAN BASMA |
| Issued | 11/4/2025 | APPLICANT |
| CofO in Progress | 3/25/2026 | DAKOTA LOW |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/11/2024 | VASIL MIHALEV |
| Address approval | Cleared | 12/23/2024 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 12/23/2024 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/24/2024 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 6/2/2025 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 12/19/2025 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 12/19/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 12/19/2025 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 12/19/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | WILBER ROSALES |
| Excavation/Setback/Form/Re-Bar | 1/6/2026 | Approved | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 1/6/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 1/6/2026 | Partial Approval | WILBER ROSALES |
| Special/Order Compliance | 1/6/2026 | Partial Inspection | DAKOTA LOW |
| Insulation | 1/16/2026 | Corrections Issued | DAKOTA LOW |
| Shower Pan | 1/16/2026 | Approved | DAKOTA LOW |
| Insulation | 1/21/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 1/21/2026 | Approved | DAKOTA LOW |
| Drywall Nailing | 2/2/2026 | Approved | DAKOTA LOW |
| Final | 3/16/2026 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 3/16/2026 | Approved | MICHAEL ALLEN |
| Green Building Final | 3/16/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Not Required | MICHAEL ALLEN |
| Smoke Detectors | 3/16/2026 | Approved | MICHAEL ALLEN |
| Final | 3/20/2026 | Corrections Issued | DAKOTA LOW |
| Final | 3/24/2026 | OK to Issue CofO | DAKOTA LOW |