4041 S MOORE ST 90066
Certificate Information: 4041 S MOORE ST 90066
- Application / Permit
- 24014-30000-05184
- Plan Check / Job No.
- B24WL09206
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to the rear of the existing single family dwelling
- Permit Issued
- Issued on 5/19/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2024 | YASHAR EMAMI |
| Corrections Issued | 12/4/2024 | YASHAR EMAMI |
| Building Plans Picked Up | 12/18/2024 | APPLICANT |
| Applicant returned to address corrections | 3/20/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/27/2025 | JOHNPAUL ISIP |
| Issued | 5/19/2025 | APPLICANT |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
| CofO Issued | 1/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/26/2024 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | A B Castle Building Contractor Inc; Lic. No.: 1011897-B | 345 S NEW HAMPSHIRE AVENUE #118 LOS ANGELES, CA 90020 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/24/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/27/2025 | Corrections Issued | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 7/21/2025 | Partial Approval | WILBER ROSALES |
| Insulation | 7/21/2025 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 7/21/2025 | Partial Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 8/15/2025 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 8/15/2025 | Approved | WILBER ROSALES |
| Rough-Elec/Plmb/HVAC | 8/15/2025 | Approved | WILBER ROSALES |
| Shower Pan | 8/15/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 8/29/2025 | Approved | WILBER ROSALES |
| Insulation | 9/2/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 9/5/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 12/5/2025 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 12/12/2025 | Approved | WILBER ROSALES |
| Final | 12/12/2025 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 12/12/2025 | Approved | WILBER ROSALES |
| Green Building Final | 12/12/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 12/12/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 12/12/2025 | Approved | WILBER ROSALES |
| Final | 1/8/2026 | Partial Approval | RUBEN RIVAS |