4557 N CAMELLIA AVE 91602
Certificate Information: 4557 N CAMELLIA AVE 91602
- Application / Permit
- 24014-30000-04965
- Plan Check / Job No.
- B24WL08750
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major remodel & 2nd floor addition to an (e) 1-story S.F.D. w/ att. garage.
- Permit Issued
- Issued on 12/24/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | ZENA HADDIS |
| Corrections Issued | 11/7/2024 | ZENA HADDIS |
| Quality Review Completed | 11/18/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/21/2024 | APPLICANT |
| Plan Check Approved | 12/11/2024 | ZENA HADDIS |
| Issued | 12/24/2024 | APPLICANT |
| CofO in Progress | 1/14/2026 | JAVIER RAMOS JR |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
| CofO Issued | 1/28/2026 | RUBEN SALAS |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 12/2/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/2/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/2/2024 | LEE GUILBEAUX |
| ZI | Cleared | 12/10/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Forefront Development Inc; Lic. No.: 809468-B | 20300 VENTURA STE 215 WOODLAND HILLS, CA 91364 |
| Engineer | Kia,, Babak; Lic. No.: C94091 | 21930 MARYLEE ST APT 87 WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 2/26/2025 | Approved | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 2/27/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Partial Approval | JAVIER RAMOS JR |
| Pre-Inspection | 5/14/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 6/5/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 6/13/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 6/20/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/20/2025 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| Underground Mechanical | 6/20/2025 | Corrections Issued | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 6/20/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/24/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/24/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/24/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/24/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/27/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/18/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/18/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/18/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 7/18/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/28/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/28/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/4/2025 | Approved | MICHAEL CORTEZ |
| Pre-Inspection | 10/27/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/9/2025 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 12/9/2025 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 12/9/2025 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 12/15/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 12/15/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 12/15/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 12/22/2025 | Approved | JAVIER RAMOS JR |
| Final | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Final | 12/22/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/22/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/22/2025 | Approved | JAVIER RAMOS JR |
| Final | 1/14/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 1/14/2026 | Approved | JAVIER RAMOS JR |