1954-1958 S PURDUE AVE 90025

Certificate Information: 1954-1958 S PURDUE AVE 90025

Application / Permit
24014-30000-04835
Plan Check / Job No.
B24WL08481
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Major Remodel, Ground, 2nd and 3rd floor addition to Create (N) 3-Story Duplex w/New Attached Garage and ADU per LAMC 12.22 A.33(c) and (e) **1 of 2**
Permit Issued
Issued on 2/12/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2024 APPLICANT
Assigned to Plan Check Engineer 10/31/2024 CHIHARU SUZUKI
Plans on Hold 10/31/2024 CHIHARU SUZUKI
Hold Released 11/1/2024 CHIHARU SUZUKI
Corrections Issued 11/4/2024 DAVID CASTILLO
Quality Review Completed 11/7/2024 CHIHARU SUZUKI
Building Plans Picked Up 11/8/2024 APPLICANT
Applicant returned to address corrections 2/6/2025 DAVID CASTILLO
Plan Check Approved 2/12/2025 DAVID CASTILLO
Issued 2/12/2025 APPLICANT
CofO in Progress 3/26/2026 RYAN SALAZAR
Permit Finaled 3/26/2026 RICHARD STEINBACH
CofO Issued 3/26/2026 RICHARD STEINBACH
Permit Finaled 3/26/2026 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 12/17/2024 ROSALINDA MEZA
Address approval Cleared 1/4/2025 LIAM ODONOVAN
Roof/Waste drainage to street Cleared 1/4/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 1/10/2025 LIAM ODONOVAN
Sewer availability Cleared 1/10/2025 LIAM ODONOVAN
Specific Plan Cleared 1/15/2025 JOSHUA JONES
DAS Clearance Cleared 1/29/2025 DAVID CASTILLO

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Quentin,, Peter Allen; Lic. No.: C32085 12516 ADMIRAL AVE      LOS ANGELES, CA 90066
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 4/9/2025 Partial Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 4/18/2025 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 4/18/2025 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Conditional Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 5/23/2025 Corrections Issued KIRK SANDERS
Deputy Reinf. Concrete 5/29/2025 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 7/14/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 7/17/2025 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 7/17/2025 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 7/29/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 7/29/2025 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 7/30/2025 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 7/30/2025 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 7/30/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 8/12/2025 Approved ARAM AVEDISIAN
HVAC-Rough 8/12/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/12/2025 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 8/13/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/13/2025 Approved ARAM AVEDISIAN
Deputy Wood Construction 8/14/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/18/2025 Not Ready for Inspection ARAM AVEDISIAN
Insulation 9/5/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/9/2025 Partial Approval ARAM AVEDISIAN
Drywall Nailing 9/12/2025 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 9/17/2025 Approved ARAM AVEDISIAN
Shower Pan 9/23/2025 Not Ready for Inspection ARAM AVEDISIAN
Shower Pan 9/24/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 10/3/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Rough 2/19/2026 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 2/19/2026 Not Ready for Inspection MICHAEL ALLEN
ELECTRICAL-Final 2/25/2026 Partial Inspection ANTHONY EGSON
HVAC-Final 2/25/2026 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 2/25/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 3/5/2026 Corrections Issued RYAN SALAZAR
HVAC-Final 3/5/2026 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 3/24/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 3/24/2026 Approved RYAN SALAZAR
Final 3/24/2026 OK to Issue CofO RYAN SALAZAR
Gas Test 3/24/2026 Approved RYAN SALAZAR
Green Building Final 3/24/2026 Approved RYAN SALAZAR
Green Building Rough 3/24/2026 Approved RYAN SALAZAR
HVAC-Final 3/24/2026 Approved RYAN SALAZAR
PLUMBING-Final 3/24/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved RYAN SALAZAR
Service/Power Release 3/24/2026 Approved RYAN SALAZAR
Smoke Detectors 3/24/2026 Approved RYAN SALAZAR