5916 N IRVINE AVE 91601
Certificate Information: 5916 N IRVINE AVE 91601
- Application / Permit
- 24014-30000-04714
- Plan Check / Job No.
- B24WL08274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) WORKSHOP AND ADD DETACHED (N) 1 STORY ADU TO (E) 2 CAR GARAGE PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 1/27/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO in Progress on 3/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2024 | JOHNPAUL ISIP |
| Corrections Issued | 10/24/2024 | JOHNPAUL ISIP |
| Building Plans Picked Up | 10/29/2024 | APPLICANT |
| Plan Check Approved | 11/22/2024 | ZENA HADDIS |
| Issued | 1/27/2025 | APPLICANT |
| CofO in Progress | 3/19/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/15/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/19/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 3/10/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/9/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 6/9/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/9/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/17/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 6/17/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 6/17/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 6/27/2025 | Partial Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 7/8/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/17/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/17/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 9/17/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/17/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/17/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 9/17/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/17/2025 | Approved | JAVIER RAMOS JR |
| Final | 3/19/2026 | OK to Issue CofO | JAVIER RAMOS JR |