5141 E MERIDIAN ST 90042
Certificate Information: 5141 E MERIDIAN ST 90042
- Application / Permit
- 24014-30000-04451
- Plan Check / Job No.
- B24WL07774
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and structural remodel to existing SFD. "COMPLY WITH DEPARTMENT ORDER effective date 09/20/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2024 | RICHARD GARCIA |
| Corrections Issued | 10/9/2024 | RICHARD GARCIA |
| Plan Check Approved | 10/18/2024 | CAROLEAN BASMA |
| Issued | 10/18/2024 | APPLICANT |
| CofO in Progress | 4/2/2025 | DANIEL DELACRUZ |
| Permit Finaled | 5/23/2025 | DANIEL SANCHEZ |
| CofO Issued | 5/23/2025 | DANIEL SANCHEZ |
| Permit Finaled | 5/23/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/15/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 10/15/2024 | JESSICA OPINION |
| Grading Pre-Inspection | Cleared | 10/17/2024 | RUSSELL BONVOULOIR |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: C92714 | 331 ARDEN AVE SUIT 201 GLENDALE, CA 91203 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/24/2024 | Corrections Issued | DANIEL DELACRUZ |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Corrections Issued | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Green Building Rough | 10/24/2024 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 10/24/2024 | Not Ready for Inspection | DANIEL DELACRUZ |
| Deputy Drilled-In Anchors | 11/13/2024 | Partial Approval | DANIEL DELACRUZ |
| Excavation/Setback/Form/Re-Bar | 11/13/2024 | Partial Approval | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 11/13/2024 | Partial Approval | DANIEL DELACRUZ |
| Excavation/Setback/Form/Re-Bar | 11/15/2024 | Partial Approval | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 11/21/2024 | Approved | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 12/11/2024 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 12/11/2024 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 12/16/2024 | Approved | DANIEL DELACRUZ |
| Sewer | 12/16/2024 | Approved | DANIEL DELACRUZ |
| Shower Pan | 12/19/2024 | Approved | DANIEL DELACRUZ |
| Insulation | 12/31/2024 | Corrections Issued | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 12/31/2024 | Approved | DANIEL DELACRUZ |
| Insulation | 1/2/2025 | Approved | DANIEL DELACRUZ |
| Drywall Nailing | 1/13/2025 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 1/16/2025 | Approved | PEDRO SIERRA |
| ELECTRICAL-Final | 3/25/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 3/25/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 3/25/2025 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | DANIEL DELACRUZ |
| Smoke Detectors | 3/25/2025 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 3/27/2025 | Approved | DANIEL DELACRUZ |
| Final | 3/27/2025 | Partial Approval | DANIEL DELACRUZ |
| Green Building Final | 3/27/2025 | Approved | DANIEL DELACRUZ |
| Non Compliance | 3/27/2025 | Not Required | DANIEL DELACRUZ |
| Final | 4/2/2025 | OK to Issue CofO | DANIEL DELACRUZ |