11429 W MCCUNE AVE 90066

Certificate Information: 11429 W MCCUNE AVE 90066

Application / Permit
24014-30000-04368
Plan Check / Job No.
B24WL07521
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO THE REAR OF (E) 1-STORY SFD AND INTERIOR REMODEL
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
Issued on 1/3/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2024 APPLICANT
Assigned to Plan Check Engineer 9/27/2024 JOHNPAUL ISIP
Corrections Issued 9/28/2024 JOHNPAUL ISIP
Building Plans Picked Up 10/4/2024 APPLICANT
Applicant returned to address corrections 11/22/2024 AMY GUEVARRA
Plan Check Approved 12/30/2024 AMY GUEVARRA
Issued 1/3/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 10/31/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 11/7/2024 DARIN LAM
Specific Plan Cleared 11/20/2024 PEDRO AYALA
Roof/Waste drainage to street Cleared 11/21/2024 ANTHONY MAINEZ
GPI Written Notices Cleared 11/22/2024 JOHNPAUL ISIP
Grading Pre-Inspection Cleared 11/22/2024 JOHNPAUL ISIP

Contact Information

Contractor Titan Builders & Remodeling Inc; Lic. No.: 1002561-B 4872 TOPANGA CANYON BLVD #402      WOODLAND HILLS, CA 91364

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/6/2025 Not Ready for Inspection DANIEL VERA
Excavation/Setback/Form/Re-Bar 1/8/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Approved DANIEL VERA
Insulation 1/22/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 1/22/2025 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/24/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 2/11/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Approved DANIEL VERA
Green Building Rough 2/11/2025 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 2/18/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Approved DANIEL VERA
Green Building Rough 2/18/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 4/9/2025 Approved WILBER ROSALES
PLUMBING-Rough 4/9/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/25/2025 Corrections Issued WILBER ROSALES
HVAC-Rough 4/25/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/29/2025 Approved WILBER ROSALES
Green Building Rough 4/29/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 4/29/2025 Approved WILBER ROSALES
Insulation 5/15/2025 Approved WILBER ROSALES
Drywall Nailing 6/26/2025 Approved WILBER ROSALES
Shower Pan 7/23/2025 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 7/25/2025 Partial Approval KIRK SANDERS
Shower Pan 7/25/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 8/1/2025 Approved MICHAEL ALLEN
Final 5/4/2026 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/4/2026 Approved ANTHONY EGSON
Green Building Final 5/4/2026 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved ANTHONY EGSON
Smoke Detectors 5/4/2026 Approved ANTHONY EGSON
ELECTRICAL-Final 5/11/2026 Corrections Issued EUGENE CASSIDY
HVAC-Final 5/11/2026 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 5/11/2026 Approved EUGENE CASSIDY