12025 W COYNE ST 90049
Certificate Information: 12025 W COYNE ST 90049
- Application / Permit
- 24014-30000-04352
- Plan Check / Job No.
- B24WL07483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to an existing S.F.D.
- Permit Issued
- Issued on 11/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2024 | RICHARD GARCIA |
| Corrections Issued | 9/28/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 10/2/2024 | APPLICANT |
| Applicant returned to address corrections | 10/21/2024 | DAVID CASTILLO |
| Plan Check Approved | 10/25/2024 | DAVID CASTILLO |
| Issued | 11/1/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 10/8/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 10/10/2024 | RICHARD GARCIA |
| Specific Plan | Cleared | 10/17/2024 | JOSHUA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/12/2024 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 12/3/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/4/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/15/2025 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 1/15/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 1/17/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/29/2025 | Conditional Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | JESUS RODRIGUEZ |
| Insulation | 2/21/2025 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 2/28/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 2/28/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/28/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/28/2025 | Approved | JESUS RODRIGUEZ |
| Final | 3/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Final | 3/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 3/21/2025 | Not Ready for Inspection | HERBERT GIRON |
| Final | 4/24/2025 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 4/24/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 4/24/2025 | Corrections Issued | HERBERT GIRON |
| Final | 7/31/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/31/2025 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 7/31/2025 | Approved | HERBERT GIRON |