1640-1642 N MURCHISON ST 90033

Certificate Information: 1640-1642 N MURCHISON ST 90033

Application / Permit
24014-30000-04308
Plan Check / Job No.
B24WL07384
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Major remodel and new 2nd story addition to (E) 1-story duplex with attached garage at front of the lot. " NFPA 13D required throughout".
Permit Issued
Issued on 2/19/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 HOOMAN HAJIZADEH
Corrections Issued 10/17/2024 HOOMAN HAJIZADEH
Quality Review Completed 10/24/2024 CHIHARU SUZUKI
Building Plans Picked Up 11/25/2024 APPLICANT
Applicant returned to address corrections 1/23/2025 HOOMAN HAJIZADEH
Plan Check Approved 2/6/2025 HOOMAN HAJIZADEH
Issued 2/19/2025 APPLICANT
CofO in Progress 4/28/2026 ALIZAH MAYAGOITIA
Permit Finaled 5/12/2026 DEROLD HAUFF
CofO Issued 5/12/2026 DEROLD HAUFF
Permit Finaled 5/12/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 11/7/2024 SARAH YOUSSEF
Highway dedication Cleared 11/8/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/13/2024 TREVOR QUAN
Sewer availability Cleared 11/13/2024 TREVOR QUAN
Frnt yard landscape/Water mgmt Cleared 11/22/2024 GEORGIA SMITH
Tenant Habitability Plan Cleared 11/25/2024 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 12/23/2024 TREVOR QUAN
Grading Pre-Inspection Cleared 1/23/2025 HOOMAN HAJIZADEH
GPI Written Notices Cleared 2/6/2025 HOOMAN HAJIZADEH

Contact Information

Architect Dehghan,, Hamid; Lic. No.: C35150 2355 WESTWOOD BLVD   # 900    LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 5/7/2025 Corrections Issued ALIZAH MAYAGOITIA
Pre-Inspection 5/7/2025 Partial Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/12/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 5/15/2025 Approved ALIZAH MAYAGOITIA
Underground Mechanical 5/27/2025 Approved ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Partial Approval ANTHONY RAMOS
Insulation 5/29/2025 Partial Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 5/30/2025 No Access for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 11/3/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/7/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/7/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/12/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 11/12/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/12/2025 Approved ALIZAH MAYAGOITIA
Drywall Nailing 12/8/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 12/8/2025 Partial Approval GEM DE OCAMPO
Interior/Exterior Lathing 12/17/2025 Approved GEM DE OCAMPO
ELECTRICAL-Final 3/16/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 3/16/2026 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 3/17/2026 Approved ALIZAH MAYAGOITIA
Final 3/17/2026 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/17/2026 Approved ALIZAH MAYAGOITIA
Green Building Final 3/17/2026 Approved ALIZAH MAYAGOITIA
HVAC-Final 3/17/2026 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/17/2026 SGSOV Not Required ALIZAH MAYAGOITIA
Smoke Detectors 3/17/2026 Approved ALIZAH MAYAGOITIA
Final 3/23/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 3/25/2026 Approved ALIZAH MAYAGOITIA
Final 4/1/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 4/27/2026 OK to Issue CofO ALIZAH MAYAGOITIA