14248-14250 W MCCORMICK ST 91401
Certificate Information: 14248-14250 W MCCORMICK ST 91401
- Application / Permit
- 24014-30000-04181
- Plan Check / Job No.
- B24WL07151
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- ADDITION TO AN (E) 1 STORY SFD WITH AN INTERIOR REMODEL. CONVERT (E) ATTACHED GARAGE INTO A JADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/1/2025
- Issuing Office
- Valley
- Current Status
- Issued on 7/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2024 | RICHARD GARCIA |
| Corrections Issued | 9/20/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 9/27/2024 | APPLICANT |
| Plan Check Approved | 4/2/2025 | JOHNPAUL ISIP |
| Issued | 7/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 3/12/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 3/12/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2025 | RYAN CASTRO |
Contact Information
| Contractor | B S M Construction Inc; Lic. No.: 828014-B | 2575 STANWELL DRIVE 2ND FLOOR CONCORD, CA 94520 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/21/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 8/12/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 10/2/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 10/3/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Insulation | 10/31/2025 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/12/2026 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 3/12/2026 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/16/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/16/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 3/20/2026 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 3/20/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/16/2026 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/16/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/29/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/29/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/30/2026 | Partial Approval | VINCENT HANLEY |
| Insulation | 6/17/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/2/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/2/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 7/2/2026 | Approved | VINCENT HANLEY |