10447 N LARAMIE AVE 91311

Certificate Information: 10447 N LARAMIE AVE 91311

Application / Permit
24014-30000-03919
Plan Check / Job No.
B24WL06737
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Attached patio covered at the rear of the (E) SFD per engineering design.
Permit Issued
Issued on 10/29/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2024 APPLICANT
Assigned to Plan Check Engineer 9/4/2024 ALFREDO JARA
Corrections Issued 9/8/2024 ALFREDO JARA
Building Plans Picked Up 9/12/2024 APPLICANT
Applicant returned to address corrections 10/1/2024 AMY GUEVARRA
Plan Check Approved 10/25/2024 JOHNPAUL ISIP
Issued 10/29/2024 APPLICANT
CofO in Progress 8/19/2025 DAVID SCANTLIN
Permit Finaled 9/16/2025 JOHN JANSON
CofO Issued 9/16/2025 JOHN JANSON
Permit Finaled 9/16/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/18/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 9/23/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/23/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/23/2024 LEE GUILBEAUX
GPI Written Notices Cleared 10/25/2024 ALFREDO JARA

Contact Information

Contractor South Coast Construction And Development; Lic. No.: 1000004-B 6380 WILSSHIRE BLVD # 1606      LOS ANGELES, CA 90048
Engineer Mah,, Edwin Poy-Dor; Lic. No.: C27141 1740 APPIAN WAY      MONTEBELLO, CA 90640

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/6/2024 Approved DAVID SCANTLIN
Sewer 11/6/2024 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 11/6/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Partial Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 12/13/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 12/13/2024 Approved DAVID SCANTLIN
Green Building Rough 12/13/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 12/13/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/20/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 8/18/2025 Approved DAVID SCANTLIN
Final 8/18/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 8/18/2025 Approved DAVID SCANTLIN
Smoke Detectors 8/18/2025 Approved DAVID SCANTLIN