12033 W ANETA ST 90230
Certificate Information: 12033 W ANETA ST 90230
- Application / Permit
- 24014-30000-03897
- Plan Check / Job No.
- B24WL06715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION OF (E) SFD WITH ATTACHED GARAGE TO ADD SECOND STORY, INCREASE GARAGE TO A 2 CAR GARAGE, ADD FRONT PORCH AND NEW DRIVEWAY.
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | ZENA HADDIS |
| Corrections Issued | 9/25/2024 | ZENA HADDIS |
| Quality Review Completed | 9/26/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/27/2024 | APPLICANT |
| Plan Check Approved | 11/6/2024 | ZENA HADDIS |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 3/26/2026 | ANTHONY EGSON |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
| CofO Issued | 4/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 10/5/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 10/5/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 10/21/2024 | DARIN LAM |
| Trees in Parkway | Cleared | 10/28/2024 | ADALBERTO VERA |
| Specific Plan | Cleared | 11/4/2024 | FREDDY GARCIA |
Contact Information
| Architect | Perazzelli,, Francesca; Lic. No.: C13717 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
| Contractor | Matthew Cook Construction; Lic. No.: 1013539-B | 1163 CHEROKEE TOPANGA, CA 90290 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 4/30/2025 | Corrections Issued | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | RUBEN RIVAS |
| Deputy Reinf. Concrete | 5/2/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/29/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 8/29/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 8/29/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 8/29/2025 | Approved | RUBEN RIVAS |
| MERV13>=Rough | 8/29/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 8/29/2025 | Approved | RUBEN RIVAS |
| Structural Steel Frame | 8/29/2025 | Corrections Issued | RUBEN RIVAS |
| Shower Pan | 9/4/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 9/17/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 9/17/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/17/2025 | Approved | RUBEN RIVAS |
| Structural Steel Frame | 9/17/2025 | Approved | RUBEN RIVAS |
| Insulation | 9/23/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 10/3/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 11/4/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 2/6/2026 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 2/6/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 2/6/2026 | Approved | ANTHONY EGSON |
| Service/Power Release | 2/6/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 2/11/2026 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 2/11/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 2/19/2026 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 3/3/2026 | Partial Approval | ANTHONY EGSON |
| HVAC-Final | 3/3/2026 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Final | 3/12/2026 | Approved | ANTHONY EGSON |
| Final | 3/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 3/12/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Final | 3/12/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 3/12/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 3/12/2026 | Approved | ANTHONY EGSON |
| Final | 3/13/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/13/2026 | Approved | ANTHONY EGSON |
| Final | 3/26/2026 | OK to Issue CofO | ANTHONY EGSON |