11950 S BEATRICE ST 90230
Certificate Information: 11950 S BEATRICE ST 90230
- Application / Permit
- 24014-30000-03887
- Plan Check / Job No.
- B24WL06689
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of (e) detached storage room to an ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/27/2025
- Issuing Office
- Current Status
- CofO Issued on 1/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2024 | RICHARD GARCIA |
| Corrections Issued | 9/4/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 9/23/2024 | APPLICANT |
| Plan Check Approved | 2/10/2025 | REZA HAGHIGHAT |
| Issued | 5/27/2025 | APPLICANT |
| CofO in Progress | 1/2/2026 | RUBEN RIVAS |
| Permit Finaled | 1/8/2026 | RICHARD STEINBACH |
| CofO Issued | 1/8/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/8/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 9/25/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 10/1/2024 | RICHARD WOO |
| Roof/Waste drainage to street | Cleared | 10/26/2024 | LIAM ODONOVAN |
| Construction near power lines | Cleared | 12/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 1543 HAWTHORNE, CA 90251 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/8/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 7/8/2025 | Approved | RUBEN RIVAS |
| Deputy Drilled-In Anchors | 7/18/2025 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/22/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 7/22/2025 | Approved | RUBEN RIVAS |
| METHANE-Barrier | 7/22/2025 | Approved | RUBEN RIVAS |
| METHANE-Subgrade | 7/22/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/25/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Rough | 8/25/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 8/25/2025 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/28/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 8/28/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 8/28/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 8/28/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 9/17/2025 | Approved | RUBEN RIVAS |
| Insulation | 9/17/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/17/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 9/19/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 9/19/2025 | Approved | JAYLIN GRAVITTE |
| Green Building Rough | 9/19/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 10/7/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 10/31/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 10/31/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 10/31/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 10/31/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | RUBEN RIVAS |
| Service/Power Release | 10/31/2025 | Order to Comply Issued | RUBEN RIVAS |
| Smoke Detectors | 10/31/2025 | Approved | RUBEN RIVAS |
| Final | 1/2/2026 | OK to Issue CofO | RUBEN RIVAS |