323 S ORANGE DR 90036
Certificate Information: 323 S ORANGE DR 90036
- Application / Permit
- 24014-30000-03840
- Plan Check / Job No.
- B24WL06589
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2nd story addition & remodel to (e) 2-story S.F.D.
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Current Status
- CofO Issued on 12/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | RICHARD GARCIA |
| Corrections Issued | 8/30/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 9/4/2024 | APPLICANT |
| Plan Check Approved | 9/10/2024 | YASHAR EMAMI |
| Issued | 9/10/2024 | APPLICANT |
| CofO in Progress | 12/9/2025 | RONNIE MINDANAO |
| Permit Finaled | 12/11/2025 | DEROLD HAUFF |
| CofO Issued | 12/11/2025 | DEROLD HAUFF |
| Permit Finaled | 12/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/3/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 9/3/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | JUSTIN BICOL |
| CPC | Cleared | 9/6/2024 | JAZMIN ROQUE |
| ZI | Cleared | 9/9/2024 | RUBEN VASQUEZ |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/28/2024 | Conditional Approval | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 10/29/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 10/29/2024 | Approved | JOSE MACIAS |
| METHANE-Barrier | 10/29/2024 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 10/29/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 12/31/2024 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 12/31/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Corrections Issued | JEFFREY MEAD |
| Deputy Wood Construction | 2/21/2025 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 2/26/2025 | Approved | RONNIE MINDANAO |
| Wood Frame | 3/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 3/28/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 4/14/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 4/15/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 4/15/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 4/16/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | RONNIE MINDANAO |
| Insulation | 4/29/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/2/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 5/2/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 5/12/2025 | Conditional Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 5/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/13/2025 | Approved | RONNIE MINDANAO |
| Insulation | 9/24/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/24/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/14/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 11/14/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 11/14/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 11/14/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 11/14/2025 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 11/18/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 11/21/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 11/21/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/21/2025 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 11/21/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | RONNIE MINDANAO |
| Final | 11/25/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 11/25/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 11/25/2025 | Approved | RONNIE MINDANAO |
| Final | 12/1/2025 | Conditional Approval | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Approved | RONNIE MINDANAO |
| Final | 12/5/2025 | OK to Issue CofO | RONNIE MINDANAO |