717 1/2 N CHEROKEE AVE 90038
Certificate Information: 717 1/2 N CHEROKEE AVE 90038
- Application / Permit
- 24014-30000-03652
- Plan Check / Job No.
- B24WL06259
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE 18'-4" x 18'-4" TO ADU WITH A GROUND FLOOR ADDITION 14'-3 x 18'-4, NEW STORAGE ROOM 5' x 12'-3" PER LAMC 12.22A33(c) & (d).
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Current Status
- CofO Issued on 3/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/19/2024 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 8/22/2024 | APPLICANT |
| Applicant returned to address corrections | 10/16/2024 | AMY GUEVARRA |
| Plan Check Approved | 10/24/2024 | YASHAR EMAMI |
| Issued | 10/30/2024 | APPLICANT |
| CofO in Progress | 3/6/2026 | CRAIG VAUGHAN |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
| CofO Issued | 3/7/2026 | DEROLD HAUFF |
| Permit Finaled | 3/7/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 10/8/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 10/8/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Corner Construction Co Inc; Lic. No.: 301167-B | 865 VIA DE LA PAZ #203 PACIFIC PALISADES, CA 90272 |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 12370 FAIRBANKS DR. TUSTIN, CA 92782 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Barrier | 1/23/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Subgrade | 1/23/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 2/6/2025 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 2/6/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/12/2025 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/12/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Barrier | 2/12/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Subgrade | 2/12/2025 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/27/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/14/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 5/14/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 5/14/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Wood Construction | 5/16/2025 | Conditional Approval | CRAIG VAUGHAN |
| Gas Test | 7/9/2025 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/9/2025 | Partial Approval | BRIAN SULLIVAN |
| Sewer | 7/9/2025 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/31/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/31/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/31/2025 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/7/2025 | Not Ready for Inspection | RAUL BARAJAS |
| METHANE-Rough | 8/7/2025 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/12/2025 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 8/12/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/21/2025 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/21/2025 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/22/2025 | Approved | CRAIG VAUGHAN |
| Shower Pan | 9/22/2025 | Approved | CRAIG VAUGHAN |
| Gas Test | 11/5/2025 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 1/22/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 1/22/2026 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 1/22/2026 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 1/22/2026 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/22/2026 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 1/22/2026 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/19/2026 | Approved | CRAIG VAUGHAN |
| Final | 2/19/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 2/19/2026 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 2/19/2026 | Approved | CRAIG VAUGHAN |
| Final | 3/5/2026 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/5/2026 | Approved | CRAIG VAUGHAN |