2019 N GRACE AVE 90068
Certificate Information: 2019 N GRACE AVE 90068
- Application / Permit
- 24014-30000-03641
- Plan Check / Job No.
- B24WL06229
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior/exterior remodel to (e) 2-story S.F.D.
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/11/2025
Permit Application Status History
| Submitted | 8/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | REZA HAGHIGHAT |
| Corrections Issued | 8/25/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 9/1/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/9/2024 | APPLICANT |
| Applicant returned to address corrections | 11/13/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 4/8/2025 | REZA HAGHIGHAT |
| Issued | 4/11/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 2/18/2025 | STEVE MELGAR |
| CPC | Cleared | 3/20/2025 | SUKI GERSHENHORN |
| HPOZ | Cleared | 3/20/2025 | SUKI GERSHENHORN |
| Grading Pre-Inspection | Cleared | 4/8/2025 | REZA HAGHIGHAT |
Contact Information
| Contractor | Chloe Construction Inc; Lic. No.: 958734-B | 5927 BALCOM AVENUE ENCINO, CA 91316 |
| Engineer | Kwan,, Denny Chi-Ho; Lic. No.: S4887 | 5638 NEWFIELDS LN DUBLIN, CA 94568 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/7/2025 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/7/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 7/7/2025 | Corrections Issued | CRAIG VAUGHAN |
| MERV13>=Rough | 7/7/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/7/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/25/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 7/25/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/21/2025 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/21/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/11/2025 | Approved | CRAIG VAUGHAN |
| Insulation | 9/11/2025 | Approved | CRAIG VAUGHAN |
| Shower Pan | 10/2/2025 | No Access for Inspection | CRAIG VAUGHAN |
| Shower Pan | 10/3/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/7/2025 | Approved | CRAIG VAUGHAN |