2723 W LOMPOC ST 90065

Certificate Information: 2723 W LOMPOC ST 90065

Application / Permit
24014-30000-03596
Plan Check / Job No.
B24WL06081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL TO (E) SFD W/ATTACHED GARAGE
Permit Issued
Issued on 11/1/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/16/2024 JOHNPAUL ISIP
Corrections Issued 8/16/2024 JOHNPAUL ISIP
Building Plans Picked Up 8/20/2024 APPLICANT
Plan Check Approved 10/29/2024 CAROLEAN BASMA
Issued 11/1/2024 APPLICANT
CofO in Progress 1/16/2026 RONNIE MEDINA
No Progress 1/16/2026 DEROLD HAUFF
CofO in Progress 1/16/2026 DEROLD HAUFF
Permit Finaled 1/21/2026 DEROLD HAUFF
CofO Issued 1/21/2026 DEROLD HAUFF
Permit Finaled 1/21/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/7/2024 ERIK BEASLEY
Sewer availability Cleared 9/16/2024 ERIK BEASLEY
Miscellaneous Cleared 10/4/2024 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/5/2024 ERIK BEASLEY
Grading Pre-Inspection Cleared 10/29/2024 MICHAEL TEMPLE

Contact Information

Contractor Flores Luis Adan; Lic. No.: 971056-B 3850 GIBRALTER AVENUE #11      LOS ANGELES, CA 90008
Engineer Basso,, Alexandre; Lic. No.: C77670 151 SOUTH EL MOLINO AVENUE, SUITE 202      PASADENA, CA 91101

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/24/2024 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 12/27/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/29/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 2/19/2025 Partial Approval BRENDAN MORELLI
Green Building Rough 2/19/2025 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 5/5/2025 Conditional Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Approved NICHOLAS LOPEZ
Green Building Rough 5/20/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Partial Approval DAVID WILLIAMS
ELECTRICAL-Rough 6/13/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 6/13/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 6/13/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 6/13/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/18/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 6/18/2025 Approved DAVID WILLIAMS
Green Building Rough 6/18/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 6/18/2025 Approved DAVID WILLIAMS
Insulation 6/30/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/30/2025 Approved REGINA MENDEZ
Drywall Nailing 7/8/2025 Approved GEM DE OCAMPO
ELECTRICAL-Final 11/17/2025 Approved RONNIE MEDINA
Final 11/17/2025 Corrections Issued RONNIE MEDINA
Green Building Final 11/17/2025 Approved RONNIE MEDINA
PLUMBING-Final 11/17/2025 Approved RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved RONNIE MEDINA
Smoke Detectors 11/17/2025 Approved RONNIE MEDINA
Final 1/14/2026 OK to Issue CofO RONNIE MEDINA