2723 W LOMPOC ST 90065
Certificate Information: 2723 W LOMPOC ST 90065
- Application / Permit
- 24014-30000-03596
- Plan Check / Job No.
- B24WL06081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO (E) SFD W/ATTACHED GARAGE
- Permit Issued
- Issued on 11/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | JOHNPAUL ISIP |
| Corrections Issued | 8/16/2024 | JOHNPAUL ISIP |
| Building Plans Picked Up | 8/20/2024 | APPLICANT |
| Plan Check Approved | 10/29/2024 | CAROLEAN BASMA |
| Issued | 11/1/2024 | APPLICANT |
| CofO in Progress | 1/16/2026 | RONNIE MEDINA |
| No Progress | 1/16/2026 | DEROLD HAUFF |
| CofO in Progress | 1/16/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/7/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/16/2024 | ERIK BEASLEY |
| Miscellaneous | Cleared | 10/4/2024 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2024 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 10/29/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Flores Luis Adan; Lic. No.: 971056-B | 3850 GIBRALTER AVENUE #11 LOS ANGELES, CA 90008 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 151 SOUTH EL MOLINO AVENUE, SUITE 202 PASADENA, CA 91101 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/24/2024 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 12/27/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/29/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 2/19/2025 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 2/19/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | BRENDAN MORELLI |
| Deputy Wood Construction | 5/5/2025 | Conditional Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 5/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2025 | Partial Approval | DAVID WILLIAMS |
| ELECTRICAL-Rough | 6/13/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 6/13/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/13/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 6/13/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/18/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 6/18/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 6/18/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 6/18/2025 | Approved | DAVID WILLIAMS |
| Insulation | 6/30/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 6/30/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 7/8/2025 | Approved | GEM DE OCAMPO |
| ELECTRICAL-Final | 11/17/2025 | Approved | RONNIE MEDINA |
| Final | 11/17/2025 | Corrections Issued | RONNIE MEDINA |
| Green Building Final | 11/17/2025 | Approved | RONNIE MEDINA |
| PLUMBING-Final | 11/17/2025 | Approved | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Approved | RONNIE MEDINA |
| Smoke Detectors | 11/17/2025 | Approved | RONNIE MEDINA |
| Final | 1/14/2026 | OK to Issue CofO | RONNIE MEDINA |