1323 S THAYER AVE 90024
Certificate Information: 1323 S THAYER AVE 90024
- Application / Permit
- 24014-30000-03342
- Plan Check / Job No.
- B24WL05521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADU ABOVE (E) GARAGEPER 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2024 | ZENA HADDIS |
| Assigned to Plan Check Engineer | 8/1/2024 | ZENA HADDIS |
| Corrections Issued | 8/29/2024 | ZENA HADDIS |
| Building Plans Picked Up | 8/30/2024 | APPLICANT |
| Quality Review Completed | 8/31/2024 | KAVIAN REFAHI |
| Quality Review Completed | 9/3/2024 | KAVIAN REFAHI |
| Plan Check Approved | 1/22/2025 | ZENA HADDIS |
| Issued | 1/22/2025 | APPLICANT |
| Permit Finaled | 2/20/2026 | RYAN SALAZAR |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 9/18/2024 | PEDRO AYALA |
| Trees in Parkway | Cleared | 10/7/2024 | MIGUEL ORNELAS |
| Low Impact Development (LID) | Cleared | 12/30/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/3/2025 | LIAM ODONOVAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 1/29/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Conditional Approval | KIRK SANDERS |
| Wood Frame | 2/4/2025 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 2/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| METHANE-Rough | 2/6/2025 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 2/19/2025 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | KIRK SANDERS |
| Wood Frame | 2/25/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 3/19/2025 | Partial Approval | DANIEL VERA |
| Gas Test | 3/19/2025 | Not Ready for Inspection | DANIEL VERA |
| PLUMBING-Rough | 3/19/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 3/21/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | KIRK SANDERS |
| Gas Test | 3/21/2025 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 3/21/2025 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 3/25/2025 | Partial Approval | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 3/25/2025 | Partial Approval | KIRK SANDERS |
| Wood Frame | 3/25/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 4/1/2025 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 4/1/2025 | Not Ready for Inspection | SEAN HAUPT |
| Gas Test | 4/2/2025 | Not Ready for Inspection | KIRK SANDERS |
| Sewer | 4/2/2025 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 4/2/2025 | Partial Approval | KIRK SANDERS |
| Deck | 4/3/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 4/3/2025 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/8/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 4/10/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/25/2025 | Partial Approval | KIRK SANDERS |
| Deputy Wood Construction | 5/1/2025 | Approved | KIRK SANDERS |
| Service/Power Release | 11/25/2025 | Approved | MICHAEL ALLEN |