2623 S BENTLEY AVE 90064

Certificate Information: 2623 S BENTLEY AVE 90064

Application / Permit
24014-30000-03155
Plan Check / Job No.
B24WL01542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Two story ADU addition to the existing detached garage per LAMC 12.22A33 (c)-(d) 2 of 2
Permit Issued
Issued on 11/21/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 ZENA HADDIS
Corrections Issued 7/31/2024 ZENA HADDIS
Quality Review Completed 8/14/2024 CHIHARU SUZUKI
Applicant returned to address corrections 11/13/2024 CHIHARU SUZUKI
Applicant returned to address corrections 11/13/2024 BEHROUZ KHOKHAR
Plan Check Approved 11/18/2024 ZENA HADDIS
Issued 11/21/2024 APPLICANT
CofO in Progress 4/28/2026 RYAN SALAZAR
Permit Finaled 4/28/2026 RICHARD STEINBACH
CofO Issued 4/28/2026 RICHARD STEINBACH
Permit Finaled 4/28/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/27/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/27/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 9/27/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 9/27/2024 KIMBERLY HERNANDEZ
GPI Written Notices Cleared 11/18/2024 ZENA HADDIS
Grading Pre-Inspection Cleared 11/18/2024 ZENA HADDIS

Contact Information

Contractor Mamos Construction & Design; Lic. No.: 1092889-B 5134 ALLENTOWN PLACE      WOODLAND HILLS, CA 91364
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/18/2024 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 12/18/2024 Not Ready for Inspection DANIEL VERA
METHANE-Barrier 12/18/2024 Not Ready for Inspection DANIEL VERA
METHANE-Subgrade 12/18/2024 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 12/31/2024 Conditional Approval BOBBY KEY
Underground Mechanical 12/31/2024 Partial Approval BOBBY KEY
Deputy Reinf. Concrete 1/2/2025 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 1/27/2025 Corrections Issued EVAN COOPER
PLUMBING-Rough 6/9/2025 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Not Ready for Inspection BOBBY KEY
HVAC-Rough 6/12/2025 Approved BOBBY KEY
BUILDING-Rough-Frame 6/30/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/30/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/30/2025 Approved BOBBY KEY
ELECTRICAL-Rough 7/8/2025 Partial Approval MEL KHACHATOURIAN
Wood Frame 7/8/2025 Conditional Approval MEL KHACHATOURIAN
Underground Mechanical 7/17/2025 Approved WILBER ROSALES
Underground Mechanical 7/29/2025 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 8/6/2025 Conditional Approval STEPHANIE SWANSON
Interior/Exterior Lathing 8/14/2025 Partial Approval TEMISTOCLES CAAL
Insulation 8/26/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 9/10/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/10/2025 Not Ready for Inspection ARAM AVEDISIAN
Shower Pan 9/10/2025 Not Ready for Inspection ARAM AVEDISIAN
Shower Pan 9/16/2025 Approved JAYLIN GRAVITTE
Service/Power Release 11/6/2025 Not Ready for Inspection MICHAEL ALLEN
Service/Power Release 1/30/2026 Partial Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 4/8/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 4/8/2026 Not Ready for Inspection RYAN SALAZAR
Final 4/8/2026 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 4/8/2026 Approved RYAN SALAZAR
Green Building Final 4/8/2026 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 4/8/2026 Approved RYAN SALAZAR
HVAC-Final 4/8/2026 Not Ready for Inspection RYAN SALAZAR
MERV13>=Final 4/8/2026 Approved RYAN SALAZAR
MERV13>=Rough 4/8/2026 Approved RYAN SALAZAR
PLUMBING-Final 4/8/2026 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 4/8/2026 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 4/8/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 4/23/2026 Approved RYAN SALAZAR
Final 4/23/2026 OK to Issue CofO RYAN SALAZAR
Green Building Final 4/23/2026 Approved RYAN SALAZAR
HVAC-Final 4/23/2026 Approved RYAN SALAZAR
PLUMBING-Final 4/23/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/23/2026 Approved RYAN SALAZAR