2623 S BENTLEY AVE 90064
Certificate Information: 2623 S BENTLEY AVE 90064
- Application / Permit
- 24014-30000-03155
- Plan Check / Job No.
- B24WL01542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Two story ADU addition to the existing detached garage per LAMC 12.22A33 (c)-(d) 2 of 2
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | ZENA HADDIS |
| Corrections Issued | 7/31/2024 | ZENA HADDIS |
| Quality Review Completed | 8/14/2024 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/13/2024 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/13/2024 | BEHROUZ KHOKHAR |
| Plan Check Approved | 11/18/2024 | ZENA HADDIS |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 4/28/2026 | RYAN SALAZAR |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
| CofO Issued | 4/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2024 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 9/27/2024 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 9/27/2024 | KIMBERLY HERNANDEZ |
| GPI Written Notices | Cleared | 11/18/2024 | ZENA HADDIS |
| Grading Pre-Inspection | Cleared | 11/18/2024 | ZENA HADDIS |
Contact Information
| Contractor | Mamos Construction & Design; Lic. No.: 1092889-B | 5134 ALLENTOWN PLACE WOODLAND HILLS, CA 91364 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/18/2024 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 12/18/2024 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Barrier | 12/18/2024 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Subgrade | 12/18/2024 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 12/31/2024 | Conditional Approval | BOBBY KEY |
| Underground Mechanical | 12/31/2024 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 1/2/2025 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/27/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/9/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 6/12/2025 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 6/30/2025 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/30/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 7/8/2025 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 7/8/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 7/17/2025 | Approved | WILBER ROSALES |
| Underground Mechanical | 7/29/2025 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/6/2025 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/14/2025 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 8/26/2025 | Approved | JAYLIN GRAVITTE |
| Drywall Nailing | 9/10/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/10/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 9/10/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 9/16/2025 | Approved | JAYLIN GRAVITTE |
| Service/Power Release | 11/6/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Service/Power Release | 1/30/2026 | Partial Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/8/2026 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/8/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 4/8/2026 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/8/2026 | Approved | RYAN SALAZAR |
| Green Building Final | 4/8/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 4/8/2026 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/8/2026 | Not Ready for Inspection | RYAN SALAZAR |
| MERV13>=Final | 4/8/2026 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 4/8/2026 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 4/8/2026 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/8/2026 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 4/8/2026 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 4/8/2026 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/23/2026 | Approved | RYAN SALAZAR |
| Final | 4/23/2026 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 4/23/2026 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/23/2026 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 4/23/2026 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 4/23/2026 | Approved | RYAN SALAZAR |