10744 W LINDBROOK DR 90024
Certificate Information: 10744 W LINDBROOK DR 90024
- Application / Permit
- 24014-30000-03104
- Plan Check / Job No.
- B24WL01521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and 1st and 2nd floor addition to existing 2-story SFD with (E) attached carport and basement
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 7/23/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 7/30/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 7/31/2024 | APPLICANT |
| Applicant returned to address corrections | 9/25/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 10/25/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 11/21/2024 | HOOMAN HAJIZADEH |
| Issued | 1/29/2025 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 10/2/2024 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 10/11/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 10/11/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2024 | DIANA RENTERIA |
| Grading Pre-Inspection | Cleared | 10/25/2024 | HOOMAN HAJIZADEH |
Contact Information
| Architect | Cunningham,, Patrick Joseph; Lic. No.: C35626 | 607 VIA LOS MIRADORES REDONDO BEACH, CA 90277 |
| Contractor | C & C Partners Design/Build Firm Inc; Lic. No.: 654337-B | 508 N PACIFIC COAST HWY REDONDO BEACH, CA 90277 |
| Engineer | Bayani-Rad,, Padra; Lic. No.: C86320 | 15901 HAWTHORNE BLVD UNIT 220 LAWNDALE, CA 90260 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 347 ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2025 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/5/2025 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 4/1/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Barrier | 4/1/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Subgrade | 4/1/2025 | Not Ready for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 4/2/2025 | Partial Approval | DANIEL VERA |
| Deputy Reinf. Concrete | 4/4/2025 | Conditional Approval | MICHAEL PELHAM |
| Underground Mechanical | 4/22/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 8/6/2025 | Corrections Issued | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 8/8/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Corrections Issued | DANIEL VERA |
| ELECTRICAL-Rough | 9/9/2025 | Approved | CHRISTOPHER WILSON |
| Gas Test | 9/11/2025 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 9/11/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/26/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | DANIEL VERA |
| Green Building Rough | 9/26/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 9/26/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Rough | 9/26/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 10/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Rough | 10/21/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 10/21/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | DANIEL VERA |
| Green Building Rough | 10/23/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 10/23/2025 | Partial Approval | DANIEL VERA |
| Wood Frame | 10/23/2025 | Approved | DANIEL VERA |
| Insulation | 11/3/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 11/3/2025 | Partial Approval | DANIEL VERA |
| Shower Pan | 11/6/2025 | Not Ready for Inspection | DANIEL VERA |
| Drywall Nailing | 11/12/2025 | Partial Approval | DANIEL VERA |
| Shower Pan | 11/12/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 11/20/2025 | Partial Approval | DANIEL VERA |
| Gas Test | 5/26/2026 | Approved | CARLOS MATAMOROS |