947 E 107TH ST 90002
Certificate Information: 947 E 107TH ST 90002
- Application / Permit
- 24014-30000-02994
- Plan Check / Job No.
- B24WL01461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) SFD and attached garage. Per engineering design.
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2024 | ALFREDO JARA |
| Corrections Issued | 7/9/2024 | ALFREDO JARA |
| Building Plans Picked Up | 7/11/2024 | APPLICANT |
| Plan Check Approved | 9/4/2024 | ALFREDO JARA |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 3/27/2025 | ANTHONY EGSON |
| Permit Finaled | 4/8/2025 | ANSON MAGLASANG |
| CofO Issued | 4/8/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/8/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/5/2024 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 8/24/2024 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/24/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/31/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/5/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 11/22/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 11/22/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/26/2024 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 11/26/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Corrections Issued | ANTHONY EGSON |
| Insulation | 12/2/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/8/2025 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 1/8/2025 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 1/8/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/10/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 1/10/2025 | Approved | ANTHONY EGSON |
| Wood Frame | 1/10/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 1/14/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/14/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 1/14/2025 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/14/2025 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 1/14/2025 | Approved | ANTHONY EGSON |
| Insulation | 1/24/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/28/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 2/25/2025 | Approved | ANSON MAGLASANG |
| Final | 2/25/2025 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 2/25/2025 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Final | 2/25/2025 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 2/25/2025 | Approved | ANSON MAGLASANG |
| Final | 3/7/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/7/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 3/26/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 3/26/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/26/2025 | Approved | ANTHONY EGSON |