3121 S OAKHURST AVE 90034
Certificate Information: 3121 S OAKHURST AVE 90034
- Application / Permit
- 24014-30000-02903
- Plan Check / Job No.
- B24WL01419
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of an (e) garage into an ADU per LAMC 12.22 A.33 (c)-(d) all work per wfpp
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2024 | RICHARD GARCIA |
| Corrections Issued | 7/9/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 7/12/2024 | APPLICANT |
| Applicant returned to address corrections | 9/30/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/8/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 1/14/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 1/15/2025 | MOHAMMAD ESMAILI |
| Issued | 1/16/2025 | APPLICANT |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 9/3/2024 | DARIN LAM |
| Sewer availability | Cleared | 9/3/2024 | DARIN LAM |
| Construction near power lines | Cleared | 12/26/2024 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 1/14/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/7/2025 | Approved | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 2/7/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/7/2025 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/6/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 3/6/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 3/6/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 3/6/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Sewer | 3/6/2025 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 3/18/2025 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/26/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 3/26/2025 | Corrections Issued | TEMISTOCLES CAAL |
| MERV13>=Rough | 3/26/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/26/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 3/26/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/2/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 4/2/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 4/2/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/2/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/8/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/8/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 4/11/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 4/11/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/11/2025 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 4/17/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/29/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Shower Pan | 4/29/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/1/2025 | Approved | ASHLEY THOMPSON |
| Shower Pan | 5/1/2025 | Approved | ASHLEY THOMPSON |
| Final | 6/25/2025 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 6/25/2025 | Approved | ASHLEY THOMPSON |
| Green Building Final | 6/25/2025 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 6/25/2025 | Approved | ASHLEY THOMPSON |
| Final | 7/1/2025 | Conditional Approval | ASHLEY THOMPSON |