8119 S STEWART AVE 90045
Certificate Information: 8119 S STEWART AVE 90045
- Application / Permit
- 24014-30000-02785
- Plan Check / Job No.
- B24WL01365
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT (E) DETACHED GARAGE TO (N) ADU PER CA Govt. Code 65852.2(e)(1)(A) ***"COMPLY WITH DEPARTMENT ORDER effective date 08/30/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".CEIS Case Number is 992322.***
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2024 | RICHARD GARCIA |
| Corrections Issued | 6/28/2024 | RICHARD GARCIA |
| Building Plans Picked Up | 7/2/2024 | APPLICANT |
| Applicant returned to address corrections | 8/20/2024 | RICHARD GARCIA |
| Plan Check Approved | 8/22/2024 | JOHNPAUL ISIP |
| Issued | 8/22/2024 | APPLICANT |
| Permit Finaled | 7/28/2025 | CLAUDIO MORENO |
| CofO Issued | 7/28/2025 | CLAUDIO MORENO |
| Permit Finaled | 7/28/2025 | CLAUDIO MORENO |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2024 | VLADIMIR ARUTYUNYAN |
| Construction near power lines | Cleared | 7/5/2024 | DANIEL ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 8/6/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 8/6/2024 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 8/15/2024 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2024 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 10/4/2024 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 10/4/2024 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 10/8/2024 | Approved | ANDREW BEELI |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | ANDREW BEELI |
| Deputy Wood Construction | 1/9/2025 | Partial Approval | ANDREW BEELI |
| ELECTRICAL-Rough | 1/14/2025 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 1/14/2025 | Approved | ANDREW BEELI |
| HVAC-Rough | 1/14/2025 | Approved | ANDREW BEELI |
| PLUMBING-Rough | 1/14/2025 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 2/4/2025 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 2/4/2025 | Not Ready for Inspection | ANDREW BEELI |
| Green Building Rough | 2/4/2025 | Not Ready for Inspection | ANDREW BEELI |
| Underground Mechanical | 2/4/2025 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 2/19/2025 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 2/19/2025 | Approved | ANDREW BEELI |
| Drywall Nailing | 3/5/2025 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 5/27/2025 | Partial Approval | ANDREW BEELI |
| ELECTRICAL-Final | 5/27/2025 | Corrections Issued | ANDREW BEELI |
| Final | 5/27/2025 | Corrections Issued | ANDREW BEELI |
| Green Building Final | 5/27/2025 | Corrections Issued | ANDREW BEELI |
| Green Building Rough | 5/27/2025 | Corrections Issued | ANDREW BEELI |
| HVAC-Final | 5/27/2025 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Final | 5/27/2025 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 5/27/2025 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 6/4/2025 | Approved | RYAN BARNES |
| Final | 6/4/2025 | Conditional Approval | RYAN BARNES |
| Green Building Final | 6/4/2025 | Approved | RYAN BARNES |
| Green Building Rough | 6/4/2025 | Approved | RYAN BARNES |
| HVAC-Final | 6/4/2025 | Approved | RYAN BARNES |
| PLUMBING-Final | 6/4/2025 | Approved | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | RYAN BARNES |