2853 N DENBY AVE 90039
Certificate Information: 2853 N DENBY AVE 90039
- Application / Permit
- 24014-30000-02361
- Plan Check / Job No.
- B24WL01183
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION AND ALTERATION TO EXISTING SINGLE FAMILY DWELLING FOR NEW ATTACHED ACCESSORY DWELLING UNIT (ADU) ORDINANCE.
- Permit Issued
- Issued on 7/12/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | SERGIO SILVA |
| Corrections Issued | 6/17/2024 | SERGIO SILVA |
| Quality Review Completed | 6/18/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 6/21/2024 | APPLICANT |
| Applicant returned to address corrections | 6/26/2024 | SERGIO SILVA |
| Plan Check Approved | 7/12/2024 | ZENA HADDIS |
| Issued | 7/12/2024 | APPLICANT |
| CofO in Progress | 7/14/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/14/2025 | DEROLD HAUFF |
| CofO Issued | 7/14/2025 | DEROLD HAUFF |
| Permit Finaled | 7/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | CELINA MORENO |
| Permit | Cleared | 6/26/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/26/2024 | CELINA MORENO |
| Sewer availability | Cleared | 6/26/2024 | CELINA MORENO |
| ZA Case | Cleared | 6/27/2024 | JASON CHAN |
| Certificate of Compliance | Cleared | 7/1/2024 | MARC WOERSCHING |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/22/2024 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/26/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Sewer | 8/28/2024 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 8/30/2024 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 9/24/2024 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/25/2024 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 9/25/2024 | Not Ready for Inspection | LUIS CASTRO |
| Insulation | 9/27/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | BRENDAN MORELLI |
| Wood Frame | 10/30/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | LUIS CASTRO |
| Pre-Inspection | 11/19/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/25/2024 | Approved | LUIS CASTRO |
| Insulation | 12/9/2024 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Rough | 12/10/2024 | Approved | LUIS CASTRO |
| HVAC-Rough | 12/10/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/11/2024 | Partial Approval | LUIS CASTRO |
| Green Building Rough | 12/11/2024 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 12/11/2024 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 1/29/2025 | Partial Approval | CRAIG DAVIS |
| Insulation | 1/31/2025 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 2/11/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 2/11/2025 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 4/1/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 6/6/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 6/6/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 6/20/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Final | 6/20/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 6/20/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 6/20/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | OSVALDO PARAMO |
| Final | 6/27/2025 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 6/27/2025 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 7/1/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 7/10/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/10/2025 | Approved | HAMIK HARTOUNIAN |