6613 W 83RD ST 90045
Certificate Information: 6613 W 83RD ST 90045
- Application / Permit
- 24014-30000-02209
- Plan Check / Job No.
- B24WL01113
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage into an ADU and addition to ADU. PerLAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/26/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | ALFREDO JARA |
| Corrections Issued | 5/24/2024 | ALFREDO JARA |
| Building Plans Picked Up | 5/31/2024 | APPLICANT |
| Applicant returned to address corrections | 11/1/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 11/19/2024 | DAVID CASTILLO |
| Plan Check Approved | 11/22/2024 | YASHAR EMAMI |
| Issued | 11/26/2024 | APPLICANT |
| CofO in Progress | 9/12/2025 | JESUS PINEDA |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
| CofO Issued | 9/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/11/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/11/2024 | RIDWAN HARDY |
| Address approval | Cleared | 10/30/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2024 | DARIN LAM |
| Sewer availability | Cleared | 10/31/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 11/5/2024 | DARIN LAM |
| Specific Plan | Cleared | 11/12/2024 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Namvar,, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/22/2025 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 1/27/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 1/30/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/20/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/27/2025 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 3/14/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 3/21/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/7/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 4/15/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 4/16/2025 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/17/2025 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/17/2025 | Approved | BOBBY KEY |
| HVAC-Rough | 4/17/2025 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | JESUS PINEDA |
| Final | 4/28/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 4/28/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | JESUS PINEDA |
| Insulation | 5/8/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/19/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/4/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 6/10/2025 | Approved | TEMISTOCLES CAAL |
| Sewer | 7/15/2025 | Approved | RUBEN RIVAS |
| Gas Test | 7/17/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 7/17/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/12/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 8/12/2025 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 8/25/2025 | Corrections Issued | JESUS PINEDA |
| Final | 8/26/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 8/26/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 8/29/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 8/29/2025 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 8/29/2025 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 9/11/2025 | Approved | JESUS PINEDA |
| Final | 9/11/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 9/11/2025 | Approved | JESUS PINEDA |
| Service/Power Release | 9/11/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 9/11/2025 | Approved | JESUS PINEDA |