460 N JUNE ST 90004

Certificate Information: 460 N JUNE ST 90004

Application / Permit
24014-30000-02192
Plan Check / Job No.
B24WL01110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert portion of garage to ADU per state law *** 2 of 2 ***
Permit Issued
Issued on 1/13/2025
Issuing Office
West Los Angeles
Current Status
Issued on 1/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 KAVIAN REFAHI
Corrections Issued 5/27/2024 KAVIAN REFAHI
Quality Review Completed 5/30/2024 CHIHARU SUZUKI
Building Plans Picked Up 5/31/2024 APPLICANT
Applicant returned to address corrections 6/24/2024 KAVIAN REFAHI
Plan Check Approved 9/4/2024 KAVIAN REFAHI
Issued 1/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/19/2024 TREVOR QUAN
Sewer availability Cleared 7/19/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 7/23/2024 TREVOR QUAN
HPOZ Cleared 8/7/2024 SUKI GERSHENHORN
Miscellaneous Cleared 8/7/2024 SUKI GERSHENHORN

Contact Information

Contractor Lopes John Build To Design; Lic. No.: 730961-B 680 E COLORADO BLVD #180      PASADENA, CA 91101
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2025 Not Ready for Inspection JEFFREY MEAD
Footing/Foundation/Slab 2/14/2025 Not Ready for Inspection JEFFREY MEAD
METHANE-Barrier 2/14/2025 Not Ready for Inspection JEFFREY MEAD
METHANE-Subgrade 2/14/2025 Not Ready for Inspection JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 2/18/2025 Corrections Issued JEFFREY MEAD
Deputy Drilled-In Anchors 2/27/2025 Conditional Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 4/17/2025 Partial Inspection JEFFREY MEAD
ELECTRICAL-Rough 4/17/2025 Approved JEFFREY MEAD
PLUMBING-Rough 4/17/2025 Not Ready for Inspection JEFFREY MEAD
Underground Mechanical 4/17/2025 Approved JEFFREY MEAD
HVAC-Rough 5/27/2025 Corrections Issued NICHOLAS LOPEZ
Wood Frame 5/27/2025 Approved NICHOLAS LOPEZ
Deputy Wood Construction 5/28/2025 Conditional Approval JEFFREY MEAD
Interior/Exterior Lathing 6/6/2025 Approved JOSH MEISTER
Insulation 6/9/2025 Corrections Issued JEFFREY MEAD
Drywall Nailing 6/17/2025 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/25/2025 Approved RONNIE MINDANAO
Shower Pan 6/25/2025 Corrections Issued RONNIE MINDANAO
Interior/Exterior Lathing 7/1/2025 Approved JOSH MEISTER
Shower Pan 7/1/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 1/26/2026 Approved JEFFREY MEAD
Final 1/26/2026 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 1/26/2026 Approved JEFFREY MEAD
Green Building Final 1/26/2026 Approved JEFFREY MEAD
Green Building Rough 1/26/2026 Approved JEFFREY MEAD
METHANE-Barrier 1/26/2026 Approved JEFFREY MEAD
METHANE-Final 1/26/2026 Approved JEFFREY MEAD
METHANE-Rough 1/26/2026 Approved JEFFREY MEAD
METHANE-Subgrade 1/26/2026 Approved JEFFREY MEAD
Smoke Detectors 1/26/2026 Approved JEFFREY MEAD