458 N JUNE ST 90004
Certificate Information: 458 N JUNE ST 90004
- Application / Permit
- 24014-30000-02191
- Plan Check / Job No.
- B24WL01110
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodel and new attached trellis with new smoker to (e) two story House *** 1 of 2 ***
- Permit Issued
- Issued on 1/13/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | KAVIAN REFAHI |
| Corrections Issued | 5/27/2024 | KAVIAN REFAHI |
| Quality Review Completed | 5/30/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 5/31/2024 | APPLICANT |
| Applicant returned to address corrections | 6/24/2024 | KAVIAN REFAHI |
| Plan Check Approved | 9/4/2024 | KAVIAN REFAHI |
| Issued | 1/13/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/19/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | TREVOR QUAN |
| HPOZ | Cleared | 8/6/2024 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 8/6/2024 | SUKI GERSHENHORN |
Contact Information
| Contractor | Lopes John Build To Design; Lic. No.: 730961-B | 680 E COLORADO BLVD #180 PASADENA, CA 91101 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/10/2025 | Conditional Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/18/2025 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 2/18/2025 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 2/18/2025 | Approved | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 2/27/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 2/27/2025 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 4/17/2025 | Approved | JEFFREY MEAD |
| Gas Test | 5/27/2025 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 5/27/2025 | Approved | NICHOLAS LOPEZ |
| Deputy Wood Construction | 5/28/2025 | Conditional Approval | JEFFREY MEAD |
| Interior/Exterior Lathing | 6/6/2025 | Approved | JOSH MEISTER |
| Insulation | 6/9/2025 | Approved | JEFFREY MEAD |
| METHANE-Final | 6/9/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 6/17/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/26/2026 | Approved | JEFFREY MEAD |
| Final | 1/26/2026 | Partial Approval | JEFFREY MEAD |
| Green Building Final | 1/26/2026 | Approved | JEFFREY MEAD |
| Green Building Rough | 1/26/2026 | Approved | JEFFREY MEAD |
| Smoke Detectors | 1/26/2026 | Approved | JEFFREY MEAD |