11340 W SUNSET BLVD 90049

Certificate Information: 11340 W SUNSET BLVD 90049

Application / Permit
24014-30000-02184
Plan Check / Job No.
B24WL01103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition (129 sf) and remodel to (e) 3-story SFD with att. 2-car garage
Permit Issued
Issued on 7/15/2024
Issuing Office
West Los Angeles
Current Status
Issued on 7/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/22/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 REZA HAGHIGHAT
Corrections Issued 5/26/2024 REZA HAGHIGHAT
Plan Check Approved 5/30/2024 REZA HAGHIGHAT
Building Plans Picked Up 5/30/2024 APPLICANT
Issued 7/15/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/22/2024 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 5/22/2024 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/30/2024 REZA HAGHIGHAT

Contact Information

Contractor Jm Builder Group Inc; Lic. No.: 1088992-B 20920 SILVERGATE WAY      NEWHALL, CA 91321
Engineer Yazdan,, Fred Faramarz; Lic. No.: C35704 32651 RACHEL CIRCLE      DANA POINT, CA 92629

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/1/2024 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 10/1/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 10/2/2024 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/7/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 10/7/2024 Approved CARLOS MATAMOROS
Underground Mechanical 10/7/2024 Not Ready for Inspection CARLOS MATAMOROS
Deputy Drilled-In Anchors 10/18/2024 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 10/18/2024 Conditional Approval CARLOS MATAMOROS
Pre-Inspection 1/17/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 3/25/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 3/28/2025 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval CARLOS MATAMOROS
Gas Test 3/28/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 4/2/2025 Approved CARLOS MATAMOROS
MERV13>=Rough 4/2/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/2/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 4/7/2025 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/7/2025 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 4/25/2025 Approved CARLOS MATAMOROS
Green Building Rough 4/25/2025 Approved CARLOS MATAMOROS
Insulation 5/2/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/2/2025 Approved CARLOS MATAMOROS
Drywall Nailing 5/21/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/4/2025 Approved CARLOS MATAMOROS