538 N LA JOLLA AVE 90048
Certificate Information: 538 N LA JOLLA AVE 90048
- Application / Permit
- 24014-30000-01946
- Plan Check / Job No.
- B24WL00992
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Renovation of an existing single story home to include a second story addition
- Permit Issued
- Issued on 6/11/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 6/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 5/22/2024 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 5/24/2024 | APPLICANT |
| Quality Review Completed | 5/25/2024 | KAVIAN REFAHI |
| Plan Check Approved | 6/7/2024 | HOOMAN HAJIZADEH |
| Issued | 6/11/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/28/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2024 | JEANIE LAM |
| Sewer availability | Cleared | 5/29/2024 | JEANIE LAM |
Contact Information
| Architect | Kelly,, Michael Kip; Lic. No.: C20478 | 9314 VENICE BLVD. CULVER CITY, CA 90232 |
| Contractor | Owner-Builder | , |
| Engineer | Alferez,, Vicente Narvaez; Lic. No.: C53875 | 460 E CARSON PLAZA DR STE 212 CARSON, CA 90746 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/8/2024 | No Access for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 7/12/2024 | Corrections Issued | AMIR NAZARIAN |
| METHANE-Barrier | 7/12/2024 | Approved | AMIR NAZARIAN |
| METHANE-Subgrade | 7/12/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 7/17/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 9/6/2024 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 9/6/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 10/11/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 10/11/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/11/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 10/17/2024 | Conditional Approval | JOSE MACIAS |
| Insulation | 10/17/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 10/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 10/23/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 10/29/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/22/2024 | Approved | JOSE MACIAS |
| Shower Pan | 11/22/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 12/6/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 12/6/2024 | Approved | JOSE MACIAS |
| Green Building Final | 12/6/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 12/6/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Ready | JOSE MACIAS |
| Drywall Nailing | 6/9/2026 | Approved | JOSH MEISTER |
| Final | 6/9/2026 | Corrections Issued | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/9/2026 | SGSOV Approved | JOSH MEISTER |
| Smoke Detectors | 6/9/2026 | Corrections Issued | JOSH MEISTER |