3267 S COLBY AVE 90066

Certificate Information: 3267 S COLBY AVE 90066

Application / Permit
24014-30000-01797
Plan Check / Job No.
B24WL00912
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel & addition of (e) S.F.R., including new 2nd floor and new attached garage.
Permit Issued
Issued on 8/22/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 YASHAR EMAMI
Corrections Issued 5/28/2024 YASHAR EMAMI
Quality Review Completed 6/4/2024 CHIHARU SUZUKI
Applicant returned to address corrections 7/30/2024 YASHAR EMAMI
Plan Check Approved 8/21/2024 YASHAR EMAMI
Issued 8/22/2024 APPLICANT
CofO in Progress 6/26/2025 ARAM AVEDISIAN
Permit Finaled 6/27/2025 RICHARD STEINBACH
CofO Issued 6/27/2025 RICHARD STEINBACH
Permit Finaled 6/27/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/2/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 7/2/2024 KIMBERLY HERNANDEZ
Low Impact Development (LID) Cleared 7/10/2024 SARAH YOUSSEF
Trees in Parkway Cleared 7/12/2024 MIGUEL ORNELAS
Permit Cleared 7/22/2024 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 7/22/2024 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 8/14/2024 FREDDY GARCIA
Grading Pre-Inspection Cleared 8/21/2024 YASHAR EMAMI
GPI Written Notices Cleared 8/22/2024 YASHAR EMAMI

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Figueroa Builders Inc; Lic. No.: 1048531-B 38045 47TH STREET EAST   SUITE E 449    PALMDALE, CA 93552
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/27/2024 Approved DANIEL VERA
ELECTRICAL-Rough 10/9/2024 Partial Approval DANIEL VERA
Footing/Foundation/Slab 10/9/2024 Approved DANIEL VERA
Deputy Steel/Welding 10/21/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/13/2024 Partial Approval DANIEL VERA
HVAC-Rough 12/26/2024 Approved SEAN HAUPT
ELECTRICAL-Final 12/30/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 12/30/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/8/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 1/8/2025 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 1/24/2025 Not Ready for Inspection DANIEL VERA
Green Building Rough 1/24/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 1/24/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Rough 1/24/2025 Approved DANIEL VERA
Shower Pan 1/24/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 1/27/2025 Conditional Approval DANIEL VERA
Shower Pan 1/27/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 1/29/2025 Approved EVAN COOPER
ELECTRICAL-Rough 1/29/2025 Approved EVAN COOPER
Green Building Rough 1/29/2025 Approved EVAN COOPER
Interior/Exterior Lathing 1/29/2025 Partial Approval EVAN COOPER
Verify Sprinkler Sign Off 1/29/2025 Approved EVAN COOPER
Insulation 1/31/2025 Approved BOBBY KEY
Interior/Exterior Lathing 1/31/2025 Approved BOBBY KEY
Drywall Nailing 2/7/2025 Approved DANIEL VERA
Gas Test 4/30/2025 Corrections Issued WILBER ROSALES
Gas Test 5/13/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 5/19/2025 Corrections Issued WILBER ROSALES
HVAC-Final 5/28/2025 Corrections Issued WILBER ROSALES
PLUMBING-Final 5/28/2025 Approved WILBER ROSALES
ELECTRICAL-Final 6/5/2025 Approved WILBER ROSALES
HVAC-Final 6/5/2025 Corrections Issued WILBER ROSALES
HVAC-Final 6/10/2025 Approved WILBER ROSALES
Final 6/26/2025 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 6/26/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 6/26/2025 Approved ARAM AVEDISIAN
Smoke Detectors 6/26/2025 Approved ARAM AVEDISIAN