6056 W 82ND ST 90045
Certificate Information: 6056 W 82ND ST 90045
- Application / Permit
- 24014-30000-01769
- Plan Check / Job No.
- B24WL00901
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to existing 1-story residence including new attached 2 car garage, remove entire bldg w/exception of wall and foundation in the front
- Permit Issued
- Issued on 9/6/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 5/14/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 5/24/2024 | KAVIAN REFAHI |
| Building Plans Picked Up | 5/31/2024 | APPLICANT |
| Applicant returned to address corrections | 8/16/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 9/3/2024 | HOOMAN HAJIZADEH |
| Issued | 9/6/2024 | APPLICANT |
| CofO in Progress | 8/3/2025 | JESUS PINEDA |
| Permit Finaled | 8/5/2025 | RICHARD STEINBACH |
| CofO Issued | 8/5/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/5/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 6/25/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 7/1/2024 | DIANA RENTERIA |
| Construction near power lines | Cleared | 7/8/2024 | ENRIQUE ACOSTA |
| Low Impact Development (LID) | Cleared | 7/9/2024 | MARCO SANCHEZ |
| Specific Plan | Cleared | 7/23/2024 | FREDDY GARCIA |
Contact Information
| Contractor | Blue Label Construction Inc; Lic. No.: 972011-B | 2632 WILSHIRE BLVD #363 SANTA MONICA, CA 90403 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2024 | Partial Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/16/2024 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 10/30/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 10/31/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 10/31/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/8/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Drilled-In Anchors | 12/19/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 1/6/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 2/4/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/4/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 2/5/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/10/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/11/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 2/11/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 2/24/2025 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 2/24/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Insulation | 2/26/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 2/28/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/28/2025 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 4/3/2025 | Not Ready for Inspection | JESUS PINEDA |
| Shower Pan | 4/3/2025 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 4/4/2025 | Approved | JESUS PINEDA |
| Shower Pan | 4/4/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 4/4/2025 | Approved | JESUS PINEDA |
| Gas Test | 5/2/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 5/2/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 5/6/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 5/6/2025 | Approved | JESUS PINEDA |
| Gas Test | 6/25/2025 | Approved | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 7/24/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 7/25/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/29/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 7/29/2025 | Approved | JESUS PINEDA |
| Final | 8/1/2025 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 8/1/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/1/2025 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 8/1/2025 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/1/2025 | Approved | JESUS PINEDA |