13040 W APPLETON WAY 90066
Certificate Information: 13040 W APPLETON WAY 90066
- Application / Permit
- 24014-30000-01700
- Plan Check / Job No.
- B24WL00863
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL OF AN (E) SFD, INCUDING THE ADDITION OF A 2ND FLOOR AND CONVERT EXISTING ATTACHED CARPORT TO ATTACHED GARAGE
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | HOOMAN HAJIZADEH |
| Corrections Issued | 5/29/2024 | HOOMAN HAJIZADEH |
| Quality Review Completed | 6/4/2024 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/5/2024 | APPLICANT |
| Applicant returned to address corrections | 7/31/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 8/16/2024 | HOOMAN HAJIZADEH |
| Issued | 8/20/2024 | APPLICANT |
| CofO in Progress | 3/27/2025 | MICHAEL ALLEN |
| Permit Finaled | 3/27/2025 | RICHARD STEINBACH |
| CofO Issued | 3/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2024 | DINAH GARIN |
| Sewer availability | Cleared | 7/3/2024 | DINAH GARIN |
| Trees in Parkway | Cleared | 7/12/2024 | MIGUEL ORNELAS |
| Roof/Waste drainage to street | Cleared | 7/22/2024 | VLADIMIR ARUTYUNYAN |
| Permit | Cleared | 7/25/2024 | DINAH GARIN |
| GPI Written Notices | Cleared | 7/31/2024 | CHIHARU SUZUKI |
| Grading Pre-Inspection | Cleared | 7/31/2024 | CHIHARU SUZUKI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Figueroa Builders Inc; Lic. No.: 1048531-B | 38045 47TH STREET EAST SUITE E 449 PALMDALE, CA 93552 |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 9/4/2024 | Partial Approval | JESUS PINEDA |
| Sewer | 9/4/2024 | Approved | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 9/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Deputy Pre-Stress Concrete | 9/19/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/1/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Wood Construction | 10/1/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 10/1/2024 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Wood Construction | 10/29/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Approved | JESUS PINEDA |
| Gas Test | 10/31/2024 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 10/31/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 10/31/2024 | Approved | JESUS PINEDA |
| Shower Pan | 10/31/2024 | Partial Approval | JESUS PINEDA |
| HVAC-Rough | 11/1/2024 | Approved | JESUS PINEDA |
| Shower Pan | 11/1/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/6/2024 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 11/8/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | JESUS PINEDA |
| Verify Sprinkler Sign Off | 11/8/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 11/13/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/14/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 11/14/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/14/2024 | Partial Approval | JESUS PINEDA |
| Insulation | 11/19/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/19/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 11/25/2024 | Approved | MICHAEL ALLEN |
| Gas Test | 12/18/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/7/2025 | Approved | JESUS PINEDA |
| Final | 3/7/2025 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 3/7/2025 | Approved | JESUS PINEDA |
| Green Building Final | 3/7/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 3/7/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 3/7/2025 | Not Ready for Inspection | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 3/7/2025 | Not Ready for Inspection | JESUS PINEDA |
| Smoke Detectors | 3/7/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 3/10/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 3/10/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 3/12/2025 | Approved | MICHAEL ALLEN |
| Final | 3/26/2025 | OK to Issue CofO | MICHAEL ALLEN |
| Service/Power Release | 3/27/2025 | Approved | DAVID FEILER |